OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 276

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 276 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J2411, De Soto Parish County
Solar
80.0 MWWithdrawn / abandoned De Soto Parish, LAMISO Sep 2022target 2026
Solar + storage project TCS-06, Fremont County
Solar + storage · Fresh Air Energy II, LLC
80.0 MWWithdrawn / abandoned Fremont, WYWest Sep 2017target 2027
Solar project J1162, Jefferson County
Solar
80.0 MWWithdrawn / abandoned Jefferson, TXMISO Mar 2018target 2020
Solar + storage project CS24-10, Spokane County
Solar + storage
80.0 MWWithdrawn / abandoned Spokane, WAWest Apr 2024target 2028
Onshore wind project GEN-2015-018, Curry County
Onshore wind
80.0 MWWithdrawn / abandoned Curry, NMSPP Mar 2015target 2016
Battery storage project J3000, Greene County
Battery storage
80.0 MWWithdrawn / abandoned Greene, INMISO Sep 2022target 2025
Lindsay Solar
Solar · HelioSage
80.0 MWWithdrawn / abandoned ERCOT Dec 2013target 2017
Onshore wind project 333, Wheatland County
Onshore wind
80.0 MWWithdrawn / abandoned Wheatland, MTWest Aug 2017target 2021
Onshore wind project GI-0304, O'brien County
Onshore wind
80.0 MWWithdrawn / abandoned O'brien, IAWest Apr 2003
Solar project G0582, Lincoln County
Solar
80.0 MWWithdrawn / abandoned Lincoln, WAWest Feb 2018target 2020
Solar project IC-1081, Walker County
Solar
80.0 MWWithdrawn / abandoned Walker, ALSoutheast Oct 2022target 2026
Onshore wind project GEN-2001-036, Quay County
Onshore wind
80.0 MWWithdrawn / abandoned Quay, NMSPP Oct 20012004
Solar + storage project IA-PNM-2023-29, Cibola County
Solar + storage
80.0 MWWithdrawn / abandoned Cibola, NMWest Sep 2023target 2029
Solar + storage project 917, Klamath County
Solar + storage
80.0 MWWithdrawn / abandoned Klamath, ORWest Jul 2017target 2019
Onshore wind project U3-025, Mineral County
Onshore wind
80.0 MWWithdrawn / abandoned Mineral, WVPJM Oct 2008target 2011
Solar project AG2-259, Fluvanna County
Solar
80.0 MWWithdrawn / abandoned Fluvanna, VAPJM Mar 2021target 2024
Onshore wind project GI-2004-8, Eagle County
Onshore wind
80.0 MWWithdrawn / abandoned Eagle, COWest Sep 2004target 2006
Hydro project G539, Bracken County
Hydro
80.0 MWWithdrawn / abandoned Bracken, KYMISO Aug 2005target 2007
Solar project J1997, Beauregard Parish County
Solar
80.0 MWWithdrawn / abandoned Beauregard Parish, LAMISO Aug 2021target 2024
Solar project IC-788, Elmore County
Solar
80.0 MWWithdrawn / abandoned Elmore, ALSoutheast Apr 2019
Onshore wind project 400, San Juan County
Onshore wind · PacifiCorp Energy
80.0 MWWithdrawn / abandoned San Juan, UTWest Sep 2011target 2013
Solar project 798, Box Elder County
Solar
80.0 MWWithdrawn / abandoned Box Elder, UTWest Sep 2016target 2019
Solar project IC-525, Chambers County
Solar
80.0 MWWithdrawn / abandoned Chambers, ALSoutheast Nov 2016
Solar project IC-462, Russell County
Solar
80.0 MWWithdrawn / abandoned Russell, ALSoutheast May 2016
Solar project AF1-278, Mckean County
Solar · McKean Solar, LLC
80.0 MWWithdrawn / abandoned Mckean, PAPJM Sep 2019target 2024
Solar + storage project C2-35, Yakima County
Solar + storage
80.0 MWWithdrawn / abandoned Yakima, WAWest Apr 2022target 2025
Solar project 285, Lowndes County
Solar
80.0 MWWithdrawn / abandoned Lowndes, MSSoutheast Mar 2016
Solar + storage project AE1-025, Bertie County
Solar + storage
80.0 MWWithdrawn / abandoned Bertie, NCPJM May 2018target 2021
Solar project IC-1028, Greene County
Solar
80.0 MWWithdrawn / abandoned Greene, MSSoutheast Mar 2022
Solar project IC-421, Henry County
Solar
80.0 MWWithdrawn / abandoned Henry, ALSoutheast Dec 2015
Orchard BESS
Battery storage · Empire Reserve Energy, LLC
80.0 MWWithdrawn / abandoned Ulster, NYNYISO Jun 2023
Battery storage project AG1-268, Essex County
Battery storage
80.0 MWWithdrawn / abandoned Essex, NJPJM Sep 2020target 2022
Solar project J2313, Sunflower County
Solar
80.0 MWWithdrawn / abandoned Sunflower, MSMISO Sep 2021target 2023
Solar project IC-1106, Walker County
Solar
80.0 MWWithdrawn / abandoned Walker, ALSoutheast Jan 2023
Solar project IC-1004, Marengo County
Solar
80.0 MWWithdrawn / abandoned Marengo, ALSoutheast Dec 2021
Battery storage project 426, Jefferson County
Battery storage
80.0 MWWithdrawn / abandoned Jefferson, MTWest Apr 2022target 2025
Onshore wind project G893, Rock County
Onshore wind
80.0 MWWithdrawn / abandoned Rock, MNMISO Oct 2007target 2010
Solar + storage project 1031, Harney County
Solar + storage
80.0 MWWithdrawn / abandoned Harney, ORWest May 2018target 2020
Solar project IC-717, Marengo County
Solar
80.0 MWWithdrawn / abandoned Marengo, ALSoutheast Jun 2018
Solar + storage project 1091, Big Horn County
Solar + storage
80.0 MWWithdrawn / abandoned Big Horn, MTWest Nov 2018target 2022
Solar project 32986, Bladen County
Solar
80.0 MWWithdrawn / abandoned Bladen, NCSoutheast Jul 2016
Solar project G0544, Umatilla County
Solar
80.0 MWWithdrawn / abandoned Umatilla, ORWest Jun 2016target 2018
Battery storage project AH1-709, Pulaski County
Battery storage · Moss Creek Solar, LLC
80.0 MWWithdrawn / abandoned Pulaski, INPJM target 2028
Onshore wind project 328, Stillwater County
Onshore wind
80.0 MWWithdrawn / abandoned Stillwater, MTWest Jul 2017target 2021
Solar project AB2-128, Northampton County
Solar
80.0 MWWithdrawn / abandoned Northampton, NCPJM Apr 2016target 2017
Solar project 18-070, Jefferson County
Solar
80.0 MWWithdrawn / abandoned Jefferson, ORWest Feb 2018target 2021
Belridge Solar Energy 2 Project
Solar
80.0 MWWithdrawn / abandoned Kern, CACAISO Apr 2012target 2016
Solar project 17658, Marion County
Solar
80.0 MWWithdrawn / abandoned Marion, SCSoutheast Oct 2017
Solano Solar
Solar
80.0 MWWithdrawn / abandoned Solano, CACAISO Mar 2011target 2014
Kimberly Run Wind Farm
Onshore wind
80.0 MWWithdrawn / abandoned Somerset, PAPJM Aug 2014target 2018
Page 276 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)