United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in the USA (2020 requests) — page 27
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Battery storage project AG2-065, Prince William County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Knickerbocker Solar Solar + storage · Naturgy Candela DevCo LLC |
20.0 MW | Withdrawn / abandoned |
| Bonny Hill Solar Solar · Oriden LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project AG1-177, Crawford County Solar |
20.0 MW | Withdrawn / abandoned |
| Hamilton Solar and BESS Solar + storage |
20.0 MW | Withdrawn / abandoned |
| Solar project AF2-438, Mercer County Solar |
20.0 MW | Withdrawn / abandoned |
| Evergreen Solar Solar |
20.0 MW | Withdrawn / abandoned |
| EX-Tidewater LLC Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AF2-344, Mercer County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project 1205, Crook County Solar |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AG1-451, Buckingham County Battery storage · RWE Solar Development, LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project AG1-144, Clearfield County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AF2-418, Columbia County Solar |
20.0 MW | Withdrawn / abandoned |
| Jade Meadow III Solar + storage |
20.0 MW | Withdrawn / abandoned |
| Solar project IC-919, Turner County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AG1-227, Schuylkill County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar + storage project AG1-083, Hertford County Solar + storage · NC-4 Ahoskie North, LLC |
20.0 MW | Withdrawn / abandoned |
| Solar + storage project AG1-278, Luzerne County Solar + storage · LU-Tank LLC |
20.0 MW | Withdrawn / abandoned |
| Solar + storage project 1227, Sweetwater County Solar + storage |
20.0 MW | Withdrawn / abandoned |
| Solar project AG1-231, Greene County Solar |
20.0 MW | Withdrawn / abandoned |
| Webb BESS Battery storage · Dimension NY 1 LLC |
20.0 MW | Withdrawn / abandoned |
| Chase Mills Solar Solar · SED NY Holdings LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project AF2-170, Erie County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AG1-557, Buckingham County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar + storage project 1196, Big Horn County Solar + storage |
20.0 MW | Withdrawn / abandoned |
| Half Moon Solar Solar + storage · Naturgy Candela DevCo LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project AG1-280, Blair County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AF2-302, Albemarle County Solar · Vista Energy Facility, LLC |
20.0 MW | Withdrawn / abandoned |
| Dover Solar and BESS Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar project Q326, Maricopa County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AG1-275, Campbell County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AG2-001, Essex County Solar |
20.0 MW | Withdrawn / abandoned |
| Hosmer Solar, LLC Solar · Granada Solar, LLC |
20.0 MW | Withdrawn / abandoned |
| Battery storage project AG1-057, Middlesex County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Hampton Corners Solar Solar · SED NY Holding LLC |
20.0 MW | Withdrawn / abandoned |
| NC1 Ahoskie Central Solar Project Solar + storage · NC1 Ahoskie Central, LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project AF2-333, Montour County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project Q325, Maricopa County Solar |
20.0 MW | Withdrawn / abandoned |
| Cedar Energy Center Battery storage |
20.0 MW | Withdrawn / abandoned |
| Solar + storage project 1230, Sweetwater County Solar + storage |
20.0 MW | Withdrawn / abandoned |
| Brockport BESS Battery storage · Saturn Energy Storage LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project 1204, Crook County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar + storage project 82, Pima County Solar + storage |
20.0 MW | Withdrawn / abandoned |
| Solar + storage project AF2-327, Sussex County Solar + storage |
20.0 MW | Withdrawn / abandoned |
| NY08 Solar Solar · Easton Solar LLC |
20.0 MW | Withdrawn / abandoned |
| Solar + storage project 1195, Big Horn County Solar + storage |
20.0 MW | Withdrawn / abandoned |
| Solar project AG1-025, Auglaize County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project C1-01, Morrow County Solar |
20.0 MW | Withdrawn / abandoned |
| Royerton Solar and Storage Battery storage · Royerton Solar, LLC |
20.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- PJM (Mid-Atlantic, Midwest)719 · 47.9 GW
- CAISO (California)107 · 46.6 GW
- West (non-ISO utilities)184 · 38.3 GW
- Southeast (non-ISO utilities)178 · 30.1 GW
- MISO (Midcontinent)195 · 27.2 GW
- NYISO (New York)129 · 25.5 GW
- SPP (Southwest Power Pool)60 · 10.4 GW
- ERCOT (Texas)67 · 10.4 GW
- ISO-NE (New England)113 · 9,841 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)