SOLAR Β· PJMSolar project AF2-418, Columbia County
Solar project AF2-418, Columbia County is a 20.0 MW solar request withdrawn in the PJM interconnection queue, in Columbia County, Pennsylvania, connecting to PPL.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2020 (completed)
- Withdrawn / abandonedSep 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AF2-418
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PPL
- Connection point (POI)
- Millville Tap 69 kV
- Location
- Columbia County, Pennsylvania
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 31 March 2020
- Proposed online date
- October 2021
- Withdrawn
- September 2023
Location
Marker shows the centre of Columbia County; the queue data does not give exact sites.
Power plants in Pennsylvania Β· Transmission lines in Pennsylvania
Other requests in Columbia County
- Frosty Valley Energy CenterSolar Β· 20.0 MW Β· agreement signed
- Stoneybrook SolarSolar Β· 19.6 MW Β· agreement signed
- Cottontail Solar 7Solar Β· 35.0 MW Β· suspended
- Mountain HollySolar Β· 20.0 MW Β· suspended
- Montour 1Solar Β· 20.0 MW Β· suspended
- Susquehanna #1Nuclear Β· 35.0 MW Β· built
- Susquehanna #1Nuclear Β· 15.0 MW Β· built
- Susquehanna #2Nuclear Β· 9.0 MW Β· built
- Susquehanna #1Nuclear Β· 9.0 MW Β· built
- Gas project AH1-675, Columbia CountyGas Β· 2,175 MW Β· withdrawn
- Gas project AH1-689, Columbia CountyGas Β· 1,450 MW Β· withdrawn
- Gas project AH1-688, Columbia CountyGas Β· 1,450 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem