🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Indiana

BATTERY STORAGE · PJM

Royerton Solar and Storage

Royerton Solar and Storage is a 20.0 MW battery storage request withdrawn in the PJM interconnection queue, in Delaware County, Indiana, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2020 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AF2-370
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Developer
Royerton Solar, LLC
Connection point (POI)
Delaware-Royerton 138 kV
Location
Delaware County, Indiana
Technology
Battery: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study
Queue status
Withdrawn
Entered queue
31 March 2020
Proposed online date
December 2023

Location

Marker shows the centre of Delaware County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Delaware County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem