Solar + storage project 1195, Big Horn County

Solar + storage project 1195, Big Horn County is a 20.0 MW solar + storage request withdrawn in the West interconnection queue, in Big Horn County, Wyoming, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2020 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1195
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Frannie substation
Location
Big Horn County, Wyoming
Technology
Solar: 20.0 MW Β· Battery
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Request assumed to be submitted to 2021 cluster
Queue status
Withdrawn
Entered queue
24 February 2020

Location

Marker shows the centre of Big Horn County; the queue data does not give exact sites.

Power plants in Wyoming Β· Transmission lines in Wyoming

Other requests in Big Horn County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem