Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,277949.5 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,277 requests · page 26 of 106
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project 693, Ada County
Solar + storage
250 MWWithdrawn / abandoned Ada, IDWest Dec 2022
Solar + storage project 129, Pima County
Solar + storage
250 MWWithdrawn / abandoned Pima, AZWest Jul 2022target 2025
Solar project GI-2017-50, Lincoln County
Solar
250 MWWithdrawn / abandoned Lincoln, COWest Nov 2017target 2022
Battery storage project GI-2021-31, Morgan County
Battery storage
250 MWWithdrawn / abandoned Morgan, COWest Oct 2021target 2024
Onshore wind project GI-0806, Stutsman County
Onshore wind
250 MWWithdrawn / abandoned Stutsman, NDWest Feb 2008target 2011
Wind + storage project IA-PNM-2025-14, Torrance County
Wind + storage
250 MWWithdrawn / abandoned Torrance, NMWest Mar 2025target 2030
Solar + storage project 645, Canyon County
Solar + storage
250 MWWithdrawn / abandoned Canyon, IDWest Mar 2022
Battery storage project C4-017, Jackson County
Battery storage
250 MWWithdrawn / abandoned Jackson, ORWest May 2024target 2028
Solar project 164, Apache County
Solar
250 MWWithdrawn / abandoned Apache, AZWest Sep 2023target 2028
Solar + storage project C1-52, Tooele County
Solar + storage
250 MWWithdrawn / abandoned Tooele, UTWest May 2021target 2024
Solar + storage project GI-2021-12, Pueblo County
Solar + storage
250 MWWithdrawn / abandoned Pueblo, COWest Sep 2021target 2024
Battery storage project Q56, Maricopa County
Battery storage
250 MWWithdrawn / abandoned Maricopa, AZWest Jan 2019target 2023
Onshore wind project GI-0705, Yankton County
Onshore wind
250 MWWithdrawn / abandoned Yankton, SDWest Mar 2007target 2009
Pacific Winds Inc
Onshore wind · Pacific Winds, Inc.
249 MWWithdrawn / abandoned Klickitat, WAWest Apr 2001target 2003
Onshore wind project G48-01, Benton County
Onshore wind · Washington Winds, Inc.
249 MWWithdrawn / abandoned Benton, WAWest Apr 2001target 2002
Onshore wind project G49, Benton County
Onshore wind · Washington Winds, Inc.
249 MWWithdrawn / abandoned Benton, WAWest Apr 2001target 2002
Onshore wind project 948, Carbon County
Onshore wind
248 MWWithdrawn / abandoned Carbon, WYWest Sep 2017target 2020
Onshore wind project 947, Carbon County
Onshore wind
248 MWWithdrawn / abandoned Carbon, WYWest Sep 2017target 2020
Onshore wind project 949, Carbon County
Onshore wind
248 MWWithdrawn / abandoned Carbon, WYWest Sep 2017target 2020
Solar + storage project C4-114, Iron County
Solar + storage
248 MWWithdrawn / abandoned Iron, UTWest May 2024target 2029
Solar + storage project Q66, Los Angeles County
Solar + storage
248 MWWithdrawn / abandoned Los Angeles, CAWest Dec 2018target 2021
Onshore wind project Q23, San Bernardino County
Onshore wind
243 MWWithdrawn / abandoned San Bernardino, CAWest Nov 2011target 2017
Onshore wind project G0280, Sherman County
Onshore wind
242 MWWithdrawn / abandoned Sherman, ORWest Jul 2007target 2011
Onshore wind project GI-0707, Mchenry County
Onshore wind
242 MWWithdrawn / abandoned Mchenry, NDWest Apr 2007target 2010
Solar project 342, Beaverhead County
Solar
240 MWWithdrawn / abandoned Beaverhead, MTWest Jun 2018target 2020
Gas project G0446, Morrow County
Gas
240 MWWithdrawn / abandoned Morrow, ORWest Dec 2010target 2013
Solar project 819, San Juan County
Solar · PacifiCorp
240 MWWithdrawn / abandoned San Juan, UTWest Nov 2016target 2019
Onshore wind project 121, Cassia County
Onshore wind
240 MWWithdrawn / abandoned Cassia, IDWest Feb 2005target 2007
Onshore wind project GI-0604, Crawford County
Onshore wind
240 MWWithdrawn / abandoned Crawford, IAWest May 2006target 2008
Onshore wind project G0405, Madison County
Onshore wind
240 MWWithdrawn / abandoned Madison, IDWest Jan 2010target 2010
Solar project 1062, Klamath County
Solar
240 MWWithdrawn / abandoned Klamath, ORWest Aug 2018target 2022
Onshore wind project 80, Rich County
Onshore wind · Iberdrola Renewables, Inc.
240 MWWithdrawn / abandoned Rich, UTWest May 2006target 2008
Gas project G0447, Morrow County
Gas
240 MWWithdrawn / abandoned Morrow, ORWest Dec 2010target 2013
Solar project 552, Elmore County
Solar
240 MWWithdrawn / abandoned Elmore, IDWest Apr 2019
Other project 734, Baker County
Other
240 MWWithdrawn / abandoned Baker, ORWest Sep 2023target 2028
Solar project GI-2018-33, Pueblo County
Solar
240 MWWithdrawn / abandoned Pueblo, COWest Sep 2018target 2021
Solar project 553, Elmore County
Solar
240 MWWithdrawn / abandoned Elmore, IDWest Apr 2019
Solar project 765, Iron County
Solar
240 MWWithdrawn / abandoned Iron, UTWest Jun 2016target 2019
Solar project GI-2016-7, Pueblo County
Solar
240 MWWithdrawn / abandoned Pueblo, COWest Apr 2016target 2018
Gas project BHCT-G1, Pueblo County
Gas · Black Hills Electric Generation LLC
240 MWWithdrawn / abandoned Pueblo, COWest Feb 2009target 2011
Onshore wind project 2007-G6
Onshore wind
240 MWWithdrawn / abandoned West Jun 2007target 2014
Solar project C3-113, Washington County
Solar
240 MWWithdrawn / abandoned Washington, UTWest May 2023target 2027
Onshore wind project G0658, Klamath County
Onshore wind
239 MWWithdrawn / abandoned Klamath, ORWest Oct 2020target 2025
Onshore wind project 1192, Klamath County
Onshore wind
239 MWWithdrawn / abandoned Klamath, ORWest Feb 2020target 2025
Other project Q613, Maricopa County
Other
232 MWWithdrawn / abandoned Maricopa, AZWest May 2025target 2026
Gas project 30, Skagit County
Gas
232 MWWithdrawn / abandoned Skagit, WAWest Feb 2011target 2014
Battery storage project 21, Sacramento County
Battery storage
230 MWWithdrawn / abandoned Sacramento, CAWest Jul 2022target 2027
Gas project 423, Salt Lake County
Gas
230 MWWithdrawn / abandoned Salt Lake, UTWest Apr 2012target 2015
Gas project 224-B, Juab County
Gas · PacifiCorp Commercial & Trading
230 MWWithdrawn / abandoned Juab, UTWest May 2008target 2013
Onshore wind project 375, Carbon County
Onshore wind
230 MWWithdrawn / abandoned Carbon, WYWest Mar 2011target 2014
Page 26 of 106

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)