ONSHORE WIND Β· WEST

Onshore wind project GI-0705, Yankton County

Onshore wind project GI-0705, Yankton County is a 250 MW onshore wind request withdrawn in the West interconnection queue, in Yankton County, South Dakota, connecting to WAPA/BEPC/HCPD Integrated System.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2007 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GI-0705
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA/BEPC/HCPD Integrated System
Connection point (POI)
Utica Jct 230kV
Location
Yankton County, South Dakota
Technology
Wind: 250 MW
Total requested
250 MW
Service type
NRIS and ERIS
Study phase
IAP
Queue status
Withdrawn
Entered queue
26 March 2007
Proposed online date
October 2009

Location

Marker shows the centre of Yankton County; the queue data does not give exact sites.

Power plants in South Dakota Β· Transmission lines in South Dakota

Other requests in Yankton County