United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in West (non-ISO utilities) — page 25

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,277949.5 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,277 requests · page 25 of 106
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project Q455, Maricopa County
Battery storage
250 MWWithdrawn / abandoned Maricopa, AZWest Mar 2022target 2025
Battery storage project 761, Elmore County
Battery storage
250 MWWithdrawn / abandoned Elmore, IDWest Apr 2025
Solar + storage project Q451, Navajo County
Solar + storage
250 MWWithdrawn / abandoned Navajo, AZWest Mar 2022target 2025
Onshore wind project BHBE G9, Weston County
Onshore wind
250 MWWithdrawn / abandoned Weston, SDWest Feb 2010target 2012
Solar project 75, Douglas County
Solar
250 MWWithdrawn / abandoned Douglas, WAWest Sep 2019target 2022
Battery storage project 22-114, Lake County
Battery storage
250 MWWithdrawn / abandoned Lake, ORWest Nov 2022target 2027
Onshore wind project 152, Lincoln County
Onshore wind · Black Canyon, LLC
250 MWWithdrawn / abandoned Lincoln, WYWest Jul 2007target 2011
Solar project 207, Yellowstone County
Solar
250 MWWithdrawn / abandoned Yellowstone, MTWest Jul 2015target 2021
Onshore wind project GI-0002, Buffalo County
Onshore wind
250 MWWithdrawn / abandoned Buffalo, SDWest Jun 2000
Solar project G0579, Jefferson County
Solar
250 MWWithdrawn / abandoned Jefferson, ORWest Dec 2017target 2021
Battery storage project 101, Pima County
Battery storage
250 MWWithdrawn / abandoned Pima, AZWest Oct 2021target 2024
Solar + storage project IA-PNM-2025-08, Curry County
Solar + storage
250 MWWithdrawn / abandoned Curry, NMWest Mar 2025target 2028
Onshore wind project GI-2008-3, Lincoln County
Onshore wind
250 MWWithdrawn / abandoned Lincoln, COWest Apr 2008target 2010
Onshore wind project GI-1006, Williams County
Onshore wind
250 MWWithdrawn / abandoned Williams, NDWest Jun 2010target 2012
Onshore wind project GI-1211, Williams County
Onshore wind
250 MWWithdrawn / abandoned Williams, NDWest Aug 2012target 2014
Onshore wind project GI-0822, Pondera County
Onshore wind
250 MWWithdrawn / abandoned Pondera, MTWest Oct 2008target 2010
Solar + storage project G0652, Umatilla County
Solar + storage
250 MWWithdrawn / abandoned Umatilla, ORWest Jul 2020target 2025
Battery storage project Q05, Maricopa County
Battery storage
250 MWWithdrawn / abandoned Maricopa, AZWest Jun 2023target 2027
Solar + storage project 1224, San Juan County
Solar + storage
250 MWWithdrawn / abandoned San Juan, UTWest Apr 2020target 2023
Solar project Q41, Yuma County
Solar
250 MWWithdrawn / abandoned Yuma, AZWest Jan 2008target 2012
Battery storage project Q03, Maricopa County
Battery storage
250 MWWithdrawn / abandoned Maricopa, AZWest Feb 2023target 2027
Solar + storage project 5, Sacramento County
Solar + storage
250 MWWithdrawn / abandoned Sacramento, CAWest Nov 2020target 2029
Solar + storage project IA-PNM-2023-21, San Juan County
Solar + storage
250 MWWithdrawn / abandoned San Juan, NMWest Sep 2023target 2028
Onshore wind project 239, Fremont County
Onshore wind
250 MWWithdrawn / abandoned Fremont, WYWest Aug 2008target 2012
Solar + storage project 720, Canyon County
Solar + storage
250 MWWithdrawn / abandoned Canyon, IDWest Jun 2023target 2027
Solar + storage project Q502, Yavapai County
Solar + storage
250 MWWithdrawn / abandoned Yavapai, AZWest Mar 2023target 2027
Solar + storage project C3-112, Oneida County
Solar + storage
250 MWWithdrawn / abandoned Oneida, IDWest May 2023target 2027
Solar project Q17, Kern County
Solar
250 MWWithdrawn / abandoned Kern, CAWest Dec 2010target 2016
Solar + storage project Q447, Yavapai County
Solar + storage
250 MWWithdrawn / abandoned Yavapai, AZWest Mar 2022target 2025
Solar + storage project Company 249, Clark County
Solar + storage
250 MWWithdrawn / abandoned Clark, NVWest Mar 2023target 2026
Solar + storage project 644, Owyhee County
Solar + storage
250 MWWithdrawn / abandoned Owyhee, IDWest Mar 2022
Solar project Q523, La Paz County
Solar
250 MWWithdrawn / abandoned La Paz, AZWest Mar 2023target 2027
Onshore wind project GI-0103, Codington County
Onshore wind
250 MWWithdrawn / abandoned Codington, SDWest Jul 2001
Solar project 2015-G1
Solar
250 MWWithdrawn / abandoned West Jul 2015target 2019
Solar + storage project 642, Minidoka County
Solar + storage
250 MWWithdrawn / abandoned Minidoka, IDWest Mar 2022
Onshore wind project 2022-G11
Onshore wind
250 MWWithdrawn / abandoned West Aug 2022target 2025
Solar + storage project 1100, Emery County
Solar + storage
250 MWWithdrawn / abandoned Emery, UTWest Jan 2019target 2021
Solar + storage project Q386, Pinal County
Solar + storage
250 MWWithdrawn / abandoned Pinal, AZWest Mar 2021target 2025
Battery storage project C4-048, Salt Lake County
Battery storage
250 MWWithdrawn / abandoned Salt Lake, UTWest May 2024target 2027
Onshore wind project 2017-G3
Onshore wind
250 MWWithdrawn / abandoned West Jan 2017target 2020
Solar project Q05, Maricopa County
Solar
250 MWWithdrawn / abandoned Maricopa, AZWest Jul 2008target 2012
Solar + storage project 647, Power County
Solar + storage
250 MWWithdrawn / abandoned Power, IDWest Mar 2022
Solar + storage project C3-110, Millard County
Solar + storage
250 MWWithdrawn / abandoned Millard, UTWest May 2023target 2027
Onshore wind project G0561, Benton County
Onshore wind
250 MWWithdrawn / abandoned Benton, WAWest May 2017target 2020
Solar project 1, Douglas County
Solar
250 MWWithdrawn / abandoned Douglas, WAWest Aug 2018target 2023
250MW Snohomish
Gas · FPL Energy Power Marketing Inc
250 MWWithdrawn / abandoned Snohomish, WAWest Jan 2001target 2002
Solar + storage project GI-2023-7, Pueblo County
Solar + storage
250 MWWithdrawn / abandoned Pueblo, COWest May 2023target 2028
Battery storage project Q449, Maricopa County
Battery storage
250 MWWithdrawn / abandoned Maricopa, AZWest Mar 2022target 2025
Onshore wind project G0307, Gilliam County
Onshore wind
250 MWWithdrawn / abandoned Gilliam, ORWest Jan 2008target 2011
Onshore wind project 55, Pondera County
Onshore wind
250 MWWithdrawn / abandoned Pondera, MTWest Mar 2007
Page 25 of 106

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)