Battery storage project 22-114, Lake County

Battery storage project 22-114, Lake County is a 250 MW battery storage request withdrawn in the West interconnection queue, in Lake County, Oregon, connecting to Portland General Electric.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
22-114
Grid region
West (non-ISO utilities)
Utility / transmission owner
Portland General Electric
Connection point (POI)
Grizzly-Ft. Rock 500 kV Line
Location
Lake County, Oregon
Technology
Battery: 250 MW
Total requested
250 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
23 November 2022
Proposed online date
December 2027

Location

Marker shows the centre of Lake County; the queue data does not give exact sites.