United States βΊ Grid βΊ Interconnection queues βΊ South Dakota
ONSHORE WIND Β· WESTOnshore wind project GI-0002, Buffalo County
Onshore wind project GI-0002, Buffalo County is a 250 MW onshore wind request withdrawn in the West interconnection queue, in Buffalo County, South Dakota, connecting to WAPA/BEPC/HCPD Integrated System.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2000 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GI-0002
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- WAPA/BEPC/HCPD Integrated System
- Connection point (POI)
- Ft Thompson
- Location
- Buffalo County, South Dakota
- Technology
- Wind: 250 MW
- Total requested
- 250 MW
- Study phase
- IAP
- Queue status
- Withdrawn
- Entered queue
- 16 June 2000
Location
Marker shows the centre of Buffalo County; the queue data does not give exact sites.
Power plants in South Dakota Β· Transmission lines in South Dakota
Other requests in Buffalo County
- Onshore wind project GI-0209, Buffalo CountyOnshore wind Β· 40.0 MW Β· built
- Onshore wind project GI-0609, Buffalo CountyOnshore wind Β· 1,500 MW Β· withdrawn
- Onshore wind project GI-0824, Buffalo CountyOnshore wind Β· 400 MW Β· withdrawn
- Solar project GEN-2022-174, Buffalo CountySolar Β· 370 MW Β· withdrawn
- Onshore wind project GI-0501, Buffalo CountyOnshore wind Β· 100 MW Β· withdrawn
- Onshore wind project GI-0121, Buffalo CountyOnshore wind Β· 30.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem