πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Washington

ONSHORE WIND Β· WEST

Onshore wind project G0561, Benton County

Onshore wind project G0561, Benton County is a 250 MW onshore wind request withdrawn in the West interconnection queue, in Benton County, Washington.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2017 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G0561
Grid region
West (non-ISO utilities)
Connection point (POI)
Badger Canyon Substation 115/230 kV. Alternates: Red Mountain Substation 115 kV; A tap on the Franklin-McNary 230 kV transmission line.
Location
Benton County, Washington
Technology
Wind: 250 MW
Total requested
250 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
3 May 2017
Proposed online date
October 2020

Location

Marker shows the centre of Benton County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Benton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem