United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2019 requests) — page 23

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,473226.5 GW
Active in queue109.2 GW589 requests
Agreement signed64.3 GW347 requests
Withdrawn1,473226.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,473 requests · page 23 of 30
ProjectCapacityStatusLocationRegionQueuedOnline
Brookfield substation - NG Western MA Area Cluster Study
Solar
24.0 MWWithdrawn / abandoned Worcester, MAISO-NE Mar 2019target 2020
Battery storage project J1429, Juneau County
Battery storage
24.0 MWWithdrawn / abandoned Juneau, WIMISO Apr 2019target 2022
Solar + storage project IA-PNM-2019-23, Luna County
Solar + storage
24.0 MWWithdrawn / abandoned Luna, NMWest Apr 2019target 2021
Solar project GEN-2019-075, Johnson County
Solar
24.0 MWWithdrawn / abandoned Johnson, NESPP May 2019target 2027
Generator reactivation
Other
24.0 MWWithdrawn / abandoned Penobscot, MEISO-NE Apr 2019target 2020
Mickleton Battery Storage
Battery storage
24.0 MWWithdrawn / abandoned Gloucester, NJPJM Nov 2019target 2028
Gas turbine repowering (Alt. to Q647)
Gas
23.0 MWWithdrawn / abandoned Middlesex, CTISO-NE Jun 2019target 2025
Solar project AE2-269, Franklin County
Solar
22.0 MWWithdrawn / abandoned Franklin, PAPJM Mar 2019target 2021
Helmer
Battery storage · Dimension NY 1 LLC
21.3 MWWithdrawn / abandoned Herkimer, NYNYISO Nov 2019
New Salem substation - NG Western MA Area Cluster Study
Solar
21.3 MWWithdrawn / abandoned Worcester, MAISO-NE Mar 2019target 2020
Stafford Street substation - NG Western MA Area Cluster Study
Solar
20.4 MWWithdrawn / abandoned Worcester, MAISO-NE Mar 2019target 2022
Battery storage project AE2-324, Marion County
Battery storage
20.3 MWWithdrawn / abandoned Marion, OHPJM Mar 2019target 2022
Fuel Cell
Gas
20.2 MWWithdrawn / abandoned Hartford, CTISO-NE Apr 2019target 2020
Fowler Solar
Solar · Granada Solar, LLC
20.0 MWWithdrawn / abandoned Madison, NYNYISO Aug 2019
Solar project AF1-149, Centre County
Solar
20.0 MWWithdrawn / abandoned Centre, PAPJM Sep 2019target 2021
Solar project AF1-154, Dauphin County
Solar
20.0 MWWithdrawn / abandoned Dauphin, PAPJM Sep 2019target 2022
Crawford Solar III
Solar
20.0 MWWithdrawn / abandoned Crawford, PAPJM Sep 2019target 2025
Solar project AE2-127, Centre County
Solar
20.0 MWWithdrawn / abandoned Centre, PAPJM Feb 2019target 2021
Madison County Solar
Solar · ConnectGen Madison County LLC
20.0 MWWithdrawn / abandoned Madison, NYNYISO May 2019
Battery storage project AF2-009, York County
Battery storage
20.0 MWWithdrawn / abandoned York, PAPJM Oct 2019target 2021
Windmill Road
Solar
20.0 MWWithdrawn / abandoned Centre, PAPJM Jan 2019target 2023
EL-Mefferts Run
Solar
20.0 MWWithdrawn / abandoned Elk, PAPJM Sep 2019target 2026
Solar project AF1-132, Centre County
Solar
20.0 MWWithdrawn / abandoned Centre, PAPJM Sep 2019target 2021
Surry Solar Center
Solar
20.0 MWWithdrawn / abandoned Surry, VAPJM May 2019target 2023
Solar project AE2-116, Adams County
Solar
20.0 MWWithdrawn / abandoned Adams, PAPJM Feb 2019target 2021
SunEast Manchester Solar LLC
Solar · SED NY Holdings LLC
20.0 MWWithdrawn / abandoned Ontario, NYNYISO Oct 2019
Turin Highlands Solar
Solar · Empire State Land Holdings, LLC
20.0 MWWithdrawn / abandoned Oneida, NYNYISO Jun 2019
Solar project AF1-171, Crawford County
Solar
20.0 MWWithdrawn / abandoned Crawford, PAPJM Sep 2019target 2023
Sithe Independence BESS
Battery storage · Vistra Operations Company, LLC
20.0 MWWithdrawn / abandoned Oswego, NYNYISO Nov 2019
Solar project AE2-252, Cumberland County
Solar
20.0 MWWithdrawn / abandoned Cumberland, PAPJM Mar 2019target 2021
Ch-Goosetown Solar
Solar
20.0 MWWithdrawn / abandoned Chester, PAPJM Sep 2019target 2022
NH Gravel Hill at Martins Creek
Solar
20.0 MWWithdrawn / abandoned Northampton, PAPJM Sep 2019target 2023
Battery storage project AF1-160, Camden County
Battery storage
20.0 MWWithdrawn / abandoned Camden, NJPJM Sep 2019target 2021
Mansfield #2
Battery storage
20.0 MWWithdrawn / abandoned Warren, NJPJM Sep 2019target 2021
Port Jeff 1-Terryville Energy Storage
Battery storage · Setauket Energy Storage, LLC
20.0 MWWithdrawn / abandoned Suffolk, NYNYISO Apr 2019
Cobleskill Solar
Solar · SWEB Development USA, LLC
20.0 MWWithdrawn / abandoned Schoharie, NYNYISO Dec 2019
Solar + storage project AF1-103, Warren County
Solar + storage
20.0 MWWithdrawn / abandoned Warren, PAPJM Sep 2019target 2023
Gas project AE2-067, Wyoming County
Gas
20.0 MWWithdrawn / abandoned Wyoming, PAPJM Feb 2019target 2021
Thomas Ridge Solar
Solar
20.0 MWWithdrawn / abandoned Snyder, PAPJM Mar 2019target 2024
Solar project AF1-334, Berks County
Solar
20.0 MWWithdrawn / abandoned Berks, PAPJM Sep 2019target 2021
Solar project AF1-214, Centre County
Solar
20.0 MWWithdrawn / abandoned Centre, PAPJM Sep 2019target 2022
Battery storage project J1252, Marquette County
Battery storage
20.0 MWWithdrawn / abandoned Marquette, MIMISO Apr 2019target 2022
Niagara Grid I
Battery storage · Niagara Grid I, LLC
20.0 MWWithdrawn / abandoned Erie, NYNYISO Nov 2019
Solar project AF1-151, Franklin County
Solar
20.0 MWWithdrawn / abandoned Franklin, PAPJM Sep 2019target 2022
Astoria Energy Storage 4
Battery storage · NRG Astoria Storage LLC
20.0 MWWithdrawn / abandoned Queens, NYNYISO May 2019
Cambria Energy
Battery storage
20.0 MWWithdrawn / abandoned Cambria, PAPJM Dec 2019target 2022
Setauket Fuel Cell
Battery storage · FourGen LLC
20.0 MWWithdrawn / abandoned Suffolk, NYNYISO Jul 2019
NY16 Solar
Solar · Boralex US Development, LLC
20.0 MWWithdrawn / abandoned Washington, NYNYISO May 2019
Solar project AF2-017, Pike County
Solar
20.0 MWWithdrawn / abandoned Pike, KYPJM Oct 2019target 2021
Solar + storage project AF2-034, Kendall County
Solar + storage · Kendall Solar BESS LLC
20.0 MWWithdrawn / abandoned Kendall, ILPJM Oct 2019target 2021
Page 23 of 30

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)