United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2016 requests) โ€” page 22

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,194150.9 GW
Active in queue25.8 GW162 requests
Agreement signed18.1 GW106 requests
Withdrawn1,194150.9 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,194 requests ยท page 22 of 24
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project AB2-137, Franklin County
Gas
4.0 MWWithdrawn / abandoned Franklin, OHPJM Apr 2016target 2017
Battery storage project AB2-030, Accomack County
Battery storage
4.0 MWWithdrawn / abandoned Accomack, VAPJM Feb 2016target 2016
Solar project AB2-088, Edgecombe County
Solar
4.0 MWWithdrawn / abandoned Edgecombe, NCPJM Apr 2016target 2016
Other project AC1-177, Queen Anne's County
Other
4.0 MWWithdrawn / abandoned Queen Anne's, MDPJM Oct 2016target 2019
Solar project AC1-014, Monmouth County
Solar
4.0 MWWithdrawn / abandoned Monmouth, NJPJM Jul 2016target 2018
Other project AC1-028, Wicomico County
Other
3.8 MWWithdrawn / abandoned Wicomico, MDPJM Jul 2016target 2017
Solar project AB2-126, Baltimore County
Solar
3.8 MWWithdrawn / abandoned Baltimore, MDPJM Apr 2016target 2017
Onshore wind project J766, Oliver County
Onshore wind
3.8 MWWithdrawn / abandoned Oliver, NDMISO Nov 2016target 2018
Onshore wind project GEN-2016-054, Jerauld County
Onshore wind
3.4 MWWithdrawn / abandoned Jerauld, SDSPP Mar 2016
Solar project AB2-125, Anne Arundel County
Solar
3.3 MWWithdrawn / abandoned Anne Arundel, MDPJM Apr 2016target 2017
Onshore wind project GEN-2016-053, Burleigh County
Onshore wind
3.3 MWWithdrawn / abandoned Burleigh, NDSPP Mar 2016target 2016
Onshore wind project GEN-2016-052, Burleigh County
Onshore wind
3.3 MWWithdrawn / abandoned Burleigh, NDSPP Mar 2016target 2016
Harris Project
Solar
3.2 MWWithdrawn / abandoned Queen Anne's, MDPJM Oct 2016target 2018
Onshore wind project MPC03500, Cavalier County
Onshore wind
3.2 MWWithdrawn / abandoned Cavalier, NDMISO Dec 2016target 2018
Solar project 242, Cascade County
Solar
3.0 MWWithdrawn / abandoned Cascade, MTWest Feb 2016target 2016
Solar project AB2-140, Harford County
Solar
3.0 MWWithdrawn / abandoned Harford, MDPJM Apr 2016target 2017
Solar project 255, Chouteau County
Solar
3.0 MWWithdrawn / abandoned Chouteau, MTWest Feb 2016target 2016
Solar project 248, Carbon County
Solar
3.0 MWWithdrawn / abandoned Carbon, MTWest Feb 2016target 2016
Onshore wind project GEN-2016-161, Carson County
Onshore wind
3.0 MWWithdrawn / abandoned Carson, TXSPP Nov 2016target 2017
Solar project 277, Chouteau County
Solar
3.0 MWWithdrawn / abandoned Chouteau, MTWest May 2016target 2017
Solar project 290, Cascade County
Solar
3.0 MWWithdrawn / abandoned Cascade, MTWest Jun 2016target 2017
Solar project 292, Silver Bow County
Solar
3.0 MWWithdrawn / abandoned Silver Bow, MTWest Jul 2016target 2020
Solar project 306, Gallatin County
Solar
3.0 MWWithdrawn / abandoned Gallatin, MTWest Nov 2016target 2020
Solar project 270, Pondera County
Solar
3.0 MWWithdrawn / abandoned Pondera, MTWest Mar 2016target 2017
Solar project 297, Judith Basin County
Solar
3.0 MWWithdrawn / abandoned Judith Basin, MTWest Jul 2016target 2017
Solar project 250, Chouteau County
Solar
3.0 MWWithdrawn / abandoned Chouteau, MTWest Feb 2016target 2016
Solar project 252, Hill County
Solar
3.0 MWWithdrawn / abandoned Hill, MTWest Feb 2016target 2016
Solar project 249, Liberty County
Solar
3.0 MWWithdrawn / abandoned Liberty, MTWest Feb 2016target 2016
Solar project 254, Cascade County
Solar
3.0 MWWithdrawn / abandoned Cascade, MTWest Feb 2016target 2016
Solar project 262, Cascade County
Solar
3.0 MWWithdrawn / abandoned Cascade, MTWest Mar 2016target 2017
Solar project 285, Silver Bow County
Solar
3.0 MWWithdrawn / abandoned Silver Bow, MTWest Jun 2016target 2020
Solar project 266, Carbon County
Solar
3.0 MWWithdrawn / abandoned Carbon, MTWest Mar 2016target 2017
Solar project 307, Madison County
Solar
3.0 MWWithdrawn / abandoned Madison, MTWest Nov 2016target 2020
Solar project 257, Chouteau County
Solar
3.0 MWWithdrawn / abandoned Chouteau, MTWest Feb 2016target 2016
Solar project AB2-018
Solar
3.0 MWWithdrawn / abandoned NCPJM Jan 2016target 2016
Solar project 808, Jackson County
Solar
3.0 MWWithdrawn / abandoned Jackson, ORWest Oct 2016target 2018
Solar project 305, Silver Bow County
Solar
3.0 MWWithdrawn / abandoned Silver Bow, MTWest Nov 2016target 2017
Solar project 289, Broadwater County
Solar
3.0 MWWithdrawn / abandoned Broadwater, MTWest Jun 2016target 2020
Solar project 246, Cascade County
Solar
3.0 MWWithdrawn / abandoned Cascade, MTWest Feb 2016target 2016
Solar project 271, Madison County
Solar
3.0 MWWithdrawn / abandoned Madison, MTWest Mar 2016target 2017
Solar project 259, Cascade County
Solar
3.0 MWWithdrawn / abandoned Cascade, MTWest Mar 2016target 2017
Solar project 293, Silver Bow County
Solar
3.0 MWWithdrawn / abandoned Silver Bow, MTWest Jul 2016target 2017
Solar project 816, Klamath County
Solar
3.0 MWWithdrawn / abandoned Klamath, ORWest Nov 2016target 2018
Solar project 256, Park County
Solar
3.0 MWWithdrawn / abandoned Park, MTWest Feb 2016target 2016
Solar project 817, Klamath County
Solar
3.0 MWWithdrawn / abandoned Klamath, ORWest Nov 2016target 2018
Solar project 281, Fergus County
Solar
3.0 MWWithdrawn / abandoned Fergus, MTWest May 2016target 2017
Solar project 260, Wheatland County
Solar
3.0 MWWithdrawn / abandoned Wheatland, MTWest Mar 2016target 2017
Solar project 269, Madison County
Solar
3.0 MWWithdrawn / abandoned Madison, MTWest Mar 2016target 2017
Solar project 294, Gallatin County
Solar
3.0 MWWithdrawn / abandoned Gallatin, MTWest Jul 2016target 2017
Solar project 278, Liberty County
Solar
3.0 MWWithdrawn / abandoned Liberty, MTWest May 2016target 2017

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)