Solar project 262, Cascade County

Solar project 262, Cascade County is a 3.0 MW solar request withdrawn in the West interconnection queue, in Cascade County, Montana, connecting to NorthWestern Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2016 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
262
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
Ulm Substation
Location
Cascade County, Montana
Technology
Solar: 3.0 MW
Total requested
3.0 MW
Service type
Energy only (ERIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
21 March 2016
Proposed online date
March 2017

Location

Marker shows the centre of Cascade County; the queue data does not give exact sites.