ONSHORE WIND Β· SPP

Onshore wind project GEN-2016-161, Carson County

Onshore wind project GEN-2016-161, Carson County is a 3.0 MW onshore wind request withdrawn in the SPP interconnection queue, in Carson County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2016 (completed)
  2. Withdrawn / abandonedApr 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2016-161
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Martin 115kV
Location
Carson County, Texas
Technology
Wind: 3.0 MW
Total requested
3.0 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 November 2016
Proposed online date
December 2017
Withdrawn
April 2021

Location

Marker shows the centre of Carson County; the queue data does not give exact sites.