United States βΊ Grid βΊ Interconnection queues βΊ North Carolina
SOLAR Β· PJMSolar project AB2-088, Edgecombe County
Solar project AB2-088, Edgecombe County is a 4.0 MW solar request withdrawn in the PJM interconnection queue, in Edgecombe County, North Carolina, connecting to Dominion.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2016 (completed)
- Withdrawn / abandonedNov 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AB2-088
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Tarboro 12.5kV
- Location
- Edgecombe County, North Carolina
- Technology
- Solar: 4.0 MW
- Total requested
- 4.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 22 April 2016
- Proposed online date
- December 2016
- Withdrawn
- November 2018
Location
Marker shows the centre of Edgecombe County; the queue data does not give exact sites.
Power plants in North Carolina Β· Transmission lines in North Carolina
Other requests in Edgecombe County
- Swift Creek SolarSolar + storage Β· 100 MW Β· agreement signed
- Lillie SolarSolar Β· 9.4 MW Β· agreement signed
- Edgecome Solar Energy CenterSolar Β· 75.0 MW Β· suspended
- Moccasin Creek SolarSolar Β· 100 MW Β· built
- Harts Mill SolarSolar Β· 80.0 MW Β· built
- Conetoe II Solar ParkSolar Β· 80.0 MW Β· built
- Solar project AE1-236, Edgecombe CountySolar Β· 290 MW Β· withdrawn
- Solar project AG1-439, Edgecombe CountySolar Β· 250 MW Β· withdrawn
- Battery storage project AF2-214, Edgecombe CountyBattery storage Β· 151 MW Β· withdrawn
- Battery storage project AG1-444, Edgecombe CountyBattery storage Β· 80.0 MW Β· withdrawn
- Solar project AH1-312, Edgecombe CountySolar Β· 80.0 MW Β· withdrawn
- Solar project AD2-089, Edgecombe CountySolar Β· 75.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem