United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in West (non-ISO utilities) — page 22
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project 926, Platte County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar + storage project G1030, Grant County Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar + storage project 2022-G9 Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar project Q044b., Maricopa County Solar |
300 MW | Withdrawn / abandoned |
| AES Pacific Inc Other · AES Pacific Inc |
300 MW | Withdrawn / abandoned |
| Solar + storage project PIS048, Utah County Solar + storage |
300 MW | Withdrawn / abandoned |
| NextEra Energy Resources Onshore wind · NextEra Energy Resources, LLC |
300 MW | Withdrawn / abandoned |
| Battery storage project Company KC, Story County Battery storage |
300 MW | Withdrawn / abandoned |
| Onshore wind project GI-2007-3, Weld County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project GI-2008-12, Kiowa County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar + storage project 2022-G10 Solar + storage |
300 MW | Withdrawn / abandoned |
| AES Pacific Inc Gas · AES Pacific Inc |
300 MW | Withdrawn / abandoned |
| Battery storage project Q71, Los Angeles County Battery storage |
300 MW | Withdrawn / abandoned |
| Solar project 997, Iron County Solar |
300 MW | Withdrawn / abandoned |
| Solar + storage project PIS035, Washington County Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar + storage project C2-75, Tooele County Solar + storage |
300 MW | Withdrawn / abandoned |
| Onshore wind project G0392, Gilliam County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar + storage project C1-23, Klamath County Solar + storage · Sugar Pine Solar Project LLC |
300 MW | Withdrawn / abandoned |
| Solar + storage project 692, Canyon County Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar + storage project Q450, Maricopa County Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar + storage project IA-PNM-2021-12, De Baca County Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar + storage project 933, Albany County Solar + storage |
300 MW | Withdrawn / abandoned |
| Solar + storage project Company JT, Pershing County Solar + storage |
300 MW | Withdrawn / abandoned |
| Onshore wind project GI-2018-15, Banner County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project 167, Natrona County Onshore wind |
299 MW | Withdrawn / abandoned |
| Onshore wind project 2007-G8 Onshore wind |
299 MW | Withdrawn / abandoned |
| Onshore wind project G0401, Wasco County Onshore wind |
299 MW | Withdrawn / abandoned |
| Onshore wind project 306-C, Converse County Onshore wind |
298 MW | Withdrawn / abandoned |
| Onshore wind project GI-2009-3, Huerfano County Onshore wind |
298 MW | Withdrawn / abandoned |
| Solar + storage project IA-PNM-2023-12, San Juan County Solar + storage |
298 MW | Withdrawn / abandoned |
| Onshore wind project GI-TC-2024-27, Sherman County Onshore wind |
298 MW | Withdrawn / abandoned |
| Gas project Q30, Pinal County Gas |
297 MW | Withdrawn / abandoned |
| Solar project Q78, Pinal County Solar |
297 MW | Withdrawn / abandoned |
| Onshore wind project G0568, Gilliam County Onshore wind |
294 MW | Withdrawn / abandoned |
| Gas project G0321, Grays Harbor County Gas |
290 MW | Withdrawn / abandoned |
| Onshore wind project 398-B, Bonneville County Onshore wind |
288 MW | Withdrawn / abandoned |
| Onshore wind project GI-0707a, Logan County Onshore wind · See 0616, 100 MW Initia |
286 MW | Withdrawn / abandoned |
| Coal project 40, Campbell County Coal |
285 MW | Withdrawn / abandoned |
| Coal project 59, Campbell County Coal · Two Elk Generation Partners, LP |
285 MW | Withdrawn / abandoned |
| Battery storage project Q91, Maricopa County Battery storage |
281 MW | Withdrawn / abandoned |
| Gas project 74, Silver Bow County Gas |
280 MW | Withdrawn / abandoned |
| Gas project 7, Cascade County Gas |
280 MW | Withdrawn / abandoned |
| Onshore wind project GI-2004-4, Prowers County Onshore wind |
280 MW | Withdrawn / abandoned |
| Onshore wind project CLPT G27, Laramie County Onshore wind |
280 MW | Withdrawn / abandoned |
| Onshore wind project 91, Golden Valley County Onshore wind |
280 MW | Withdrawn / abandoned |
| Onshore wind project GI-2005-1, Prowers County Onshore wind |
279 MW | Withdrawn / abandoned |
| Gas project 53, Cascade County Gas |
277 MW | Withdrawn / abandoned |
| Onshore wind project GI-2018-22, Elbert County Onshore wind |
276 MW | Withdrawn / abandoned |
| Other project 18, Payette County Other |
275 MW | Withdrawn / abandoned |
| Other project 17, Washington County Other |
275 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 · 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 · 638.1 GW
- MISO (Midcontinent)3,261 · 621.9 GW
- CAISO (California)2,186 · 619.9 GW
- Southeast (non-ISO utilities)2,738 · 603.3 GW
- SPP (Southwest Power Pool)1,846 · 382.9 GW
- NYISO (New York)1,531 · 324.1 GW
- ERCOT (Texas)1,158 · 262.0 GW
- ISO-NE (New England)982 · 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)