SOLAR + STORAGE Β· WESTSolar + storage project IA-PNM-2021-12, De Baca County
Solar + storage project IA-PNM-2021-12, De Baca County is a 300 MW solar + storage request withdrawn in the West interconnection queue, in De Baca County, New Mexico, connecting to Public Service Company of New Mexico.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2021 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IA-PNM-2021-12
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Public Service Company of New Mexico
- Connection point (POI)
- Taiban 345 kV Substation
- Location
- De Baca County, New Mexico
- Technology
- Solar: 300 MW Β· Battery
- Total requested
- 300 MW
- Service type
- Energy only (ERIS)
- Queue status
- Withdrawn
- Entered queue
- 8 July 2021
- Proposed online date
- June 2025
Location
Marker shows the centre of De Baca County; the queue data does not give exact sites.
Power plants in New Mexico Β· Transmission lines in New Mexico