United States βΊ Grid βΊ Interconnection queues βΊ California
OTHER Β· WESTAES Pacific Inc
AES Pacific Inc is a 300 MW other request withdrawn in the West interconnection queue, in Modoc County, California, connecting to AES Pacific Inc.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2001 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G71
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- AES Pacific Inc
- Developer
- AES Pacific Inc
- Connection point (POI)
- BPA's Canby 230 kV Substation in Modoc County, CA.
- Location
- Modoc County, California
- Technology
- Other: 300 MW
- Total requested
- 300 MW
- Service type
- Energy only (ERIS)
- Queue status
- Withdrawn
- Entered queue
- 17 August 2001
- Proposed online date
- June 2002
Location
Marker shows the centre of Modoc County; the queue data does not give exact sites.
Power plants in California Β· Transmission lines in California
Other requests in Modoc County
- Solar + storage project T2-078, Modoc CountySolar + storage Β· 24.9 MW Β· in study
- Solar + storage project G0868, Modoc CountySolar + storage Β· 400 MW Β· withdrawn
- Solar project G0547, Modoc CountySolar Β· 80.0 MW Β· withdrawn
- Solar + storage project 1160, Modoc CountySolar + storage Β· 60.0 MW Β· withdrawn
- Solar + storage project C1-41, Modoc CountySolar + storage Β· 60.0 MW Β· withdrawn
- Solar + storage project TCS-42, Modoc CountySolar + storage Β· 60.0 MW Β· withdrawn
- Cal GeoGeothermal Β· 30.0 MW Β· withdrawn
- Solar + storage project C4-112, Modoc CountySolar + storage Β· 24.9 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem