SOLAR Β· WESTSolar project G0547, Modoc County
Solar project G0547, Modoc County is a 80.0 MW solar request withdrawn in the West interconnection queue, in Modoc County, California.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2016 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G0547
- Grid region
- West (non-ISO utilities)
- Connection point (POI)
- BPA Canby-Surprise Valley Electric Substation (SVE) 69 kV bus, via a tie line, or the SVE Co-op system.
- Location
- Modoc County, California
- Technology
- Solar: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 20 June 2016
- Proposed online date
- April 2019
Location
Marker shows the centre of Modoc County; the queue data does not give exact sites.
Power plants in California Β· Transmission lines in California
Other requests in Modoc County
- Solar + storage project T2-078, Modoc CountySolar + storage Β· 24.9 MW Β· in study
- Solar + storage project G0868, Modoc CountySolar + storage Β· 400 MW Β· withdrawn
- AES Pacific IncOther Β· 300 MW Β· withdrawn
- Solar + storage project 1160, Modoc CountySolar + storage Β· 60.0 MW Β· withdrawn
- Solar + storage project C1-41, Modoc CountySolar + storage Β· 60.0 MW Β· withdrawn
- Solar + storage project TCS-42, Modoc CountySolar + storage Β· 60.0 MW Β· withdrawn
- Cal GeoGeothermal Β· 30.0 MW Β· withdrawn
- Solar + storage project C4-112, Modoc CountySolar + storage Β· 24.9 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem