πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR + STORAGE Β· WEST

Solar + storage project C4-112, Modoc County

Solar + storage project C4-112, Modoc County is a 24.9 MW solar + storage request withdrawn in the West interconnection queue, in Modoc County, California, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2024 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
C4-112
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Alturas - Mile Hi transmission line
Location
Modoc County, California
Technology
Solar: 24.9 MW Β· Battery
Total requested
24.9 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
15 May 2024
Proposed online date
December 2026

Location

Marker shows the centre of Modoc County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Modoc County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem