πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New Mexico

SOLAR + STORAGE Β· WEST

Solar + storage project IA-PNM-2023-12, San Juan County

Solar + storage project IA-PNM-2023-12, San Juan County is a 298 MW solar + storage request withdrawn in the West interconnection queue, in San Juan County, New Mexico, connecting to Public Service Company of New Mexico.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2023 (completed)
  2. Withdrawn / abandonedNov 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IA-PNM-2023-12
Grid region
West (non-ISO utilities)
Utility / transmission owner
Public Service Company of New Mexico
Connection point (POI)
San Juan 345 kV Substation
Location
San Juan County, New Mexico
Technology
Solar: 198 MW Β· Battery: 100 MW
Total requested
298 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
3 January 2023
Proposed online date
December 2027
Withdrawn
November 2023

Location

Marker shows the centre of San Juan County; the queue data does not give exact sites.

Power plants in New Mexico Β· Transmission lines in New Mexico

Other requests in San Juan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem