United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in the USA (2023 requests) — page 20

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,249298.6 GW
Active in queue298.6 GW1,249 requests
Agreement signed34.6 GW168 requests
Withdrawn2,063551.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,249 requests · page 20 of 25
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 526, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2029
Battery storage project 223, Williamsburg County
Battery storage
74.5 MWIn study Williamsburg, SCSoutheast Jun 2023target 2028
Solar project 545, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2031
Solar project 515, Charlotte County
Solar · FPL
74.5 MWIn study Charlotte, FLSoutheast Jan 2023target 2030
Solar project 595, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Jul 2023target 2031
Solar project 523, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2028
Solar project 570, Collier County
Solar · FPL
74.5 MWIn study Collier, FLSoutheast Jul 2023target 2031
Solar project 593, Martin County
Solar · FPL
74.5 MWIn study Martin, FLSoutheast Jul 2023target 2030
Solar project 530, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2030
Solar project 513, Charlotte County
Solar · FPL
74.5 MWIn study Charlotte, FLSoutheast Jan 2023target 2030
Solar project 552, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2032
Solar project 564, Collier County
Solar · FPL
74.5 MWIn study Collier, FLSoutheast Jul 2023target 2032
Solar project 490, St. Lucie County
Solar · FPL
74.5 MWIn study St. Lucie, FLSoutheast Jan 2023target 2029
Solar project 543, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2031
Solar project 561, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jul 2023target 2030
Solar project 521, Desoto County
Solar · FPL
74.5 MWIn study Desoto, FLSoutheast Jan 2023target 2030
Solar project 500, Martin County
Solar · FPL
74.5 MWIn study Martin, FLSoutheast Jan 2023target 2030
Solar project 496, Martin County
Solar · FPL
74.5 MWIn study Martin, FLSoutheast Jan 2023target 2029
Solar project 559, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jul 2023target 2032
Solar project 516, Charlotte County
Solar · FPL
74.5 MWIn study Charlotte, FLSoutheast Jan 2023target 2030
Solar project 550, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2032
Solar project 528, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2029
Solar project 514, Charlotte County
Solar · FPL
74.5 MWIn study Charlotte, FLSoutheast Jan 2023target 2030
Solar project 544, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2031
Solar project 499, Martin County
Solar · FPL
74.5 MWIn study Martin, FLSoutheast Jan 2023target 2030
Solar project 563, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jul 2023target 2030
Solar project 558, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jul 2023target 2032
Solar project 562, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jul 2023target 2030
Solar project 524, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2028
Solar project 571, Collier County
Solar · FPL
74.5 MWIn study Collier, FLSoutheast Jul 2023target 2031
Solar project 594, Indian River County
Solar · FPL
74.5 MWIn study Indian River, FLSoutheast Jul 2023target 2029
Solar project 567, Collier County
Solar · FPL
74.5 MWIn study Collier, FLSoutheast Jul 2023target 2032
Solar project 527, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2029
Solar project 531, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2030
Solar project 539, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2031
Solar project 505, Martin County
Solar · FPL
74.5 MWIn study Martin, FLSoutheast Jan 2023target 2030
Solar project 522, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2028
Solar project 540, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2031
Solar project 506, Martin County
Solar · FPL
74.5 MWIn study Martin, FLSoutheast Jan 2023target 2030
Solar project 549, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2032
Solar project 492, Indian River County
Solar · FPL
74.5 MWIn study Indian River, FLSoutheast Jan 2023target 2028
Solar project 535, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2031
Solar project 532, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2030
Solar project 548, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2032
Solar project 525, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2028
Solar project 520, Charlotte County
Solar · FPL
74.5 MWIn study Charlotte, FLSoutheast Jan 2023target 2031
Solar project 498, Martin County
Solar · FPL
74.5 MWIn study Martin, FLSoutheast Jan 2023target 2029
Solar project 502, Martin County
Solar · FPL
74.5 MWIn study Martin, FLSoutheast Jan 2023target 2030
Solar project 538, Hendry County
Solar · FPL
74.5 MWIn study Hendry, FLSoutheast Jan 2023target 2031
Solar project 509, Manatee County
Solar · FPL
74.5 MWIn study Manatee, FLSoutheast Jan 2023target 2030
Page 20 of 25

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)