United States › Grid › Interconnection queues › Florida
SOLAR · SOUTHEASTSolar project 492, Indian River County
Solar project 492, Indian River County is a 74.5 MW solar request in interconnection study in the Southeast interconnection queue, in Indian River County, Florida, connecting to Florida Power & Light.
- PlanningQueued Jan 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jan 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 492
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Florida Power & Light
- Developer
- FPL
- Connection point (POI)
- Southern Indian River County
- Location
- Indian River County, Florida
- Technology
- Solar: 74.5 MW
- Total requested
- 74.5 MW
- Service type
- Network resource (NRIS)
- Study phase
- Facility Study
- Queue status
- Active
- Entered queue
- 6 January 2023
- Proposed online date
- January 2028
Location
Marker shows the centre of Indian River County; the queue data does not give exact sites.
Other requests in Indian River County
- Solar project 493, Indian River CountySolar · 74.5 MW · in study
- Solar project 456, Indian River CountySolar · 74.5 MW · in study
- Solar project 594, Indian River CountySolar · 74.5 MW · in study
- Solar project 432, Indian River CountySolar · 74.5 MW · in study
- Solar project 452, Indian River CountySolar · 74.5 MW · in study
- Solar project 491, Indian River CountySolar · 74.5 MW · in study
- Solar project 427, Indian River CountySolar · 74.5 MW · in study
- Solar project 285, Indian River CountySolar · 74.5 MW · built
- Solar project 297, Indian River CountySolar · 74.5 MW · built
- Solar project 286, Indian River CountySolar · 74.5 MW · built
- Battery storage project 626, Indian River CountyBattery storage · 400 MW · withdrawn
- Battery storage project 624, Indian River CountyBattery storage · 300 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem