🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in NYISO (New York) — page 20

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,531324.1 GW
Active in queue27.1 GW190 requests
Agreement signed0.0 MW0 requests
Withdrawn1,531324.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,531 requests · page 20 of 31
ProjectCapacityStatusLocationRegionQueuedOnline
Black Oak Wind
Onshore wind · Enfield Energy, LLC
50.0 MWWithdrawn / abandoned Tompkins, NYNYISO Jun 2009
Suffragette Solar Energy Center
Solar · EDF Renewables Development, Inc.
50.0 MWWithdrawn / abandoned Seneca, NYNYISO Jun 2021
Deerpark Energy Storage
Battery storage · Deerpark Energy Storage
50.0 MWWithdrawn / abandoned Orange, NYNYISO Jan 2024
Azalea Wind 1
Onshore wind · Azalea Wind LLC
50.0 MWWithdrawn / abandoned Schuyler, NYNYISO Sep 2024
Kce NY 30
Battery storage · KCE NY 30, LLC
50.0 MWWithdrawn / abandoned Suffolk, NYNYISO Oct 2022
Cortland Energy Center
Solar · Cortland Energy Center, LLC
50.0 MWWithdrawn / abandoned Cortland, NYNYISO Jun 2018
Loomis Creek ES
Battery storage · sPower Development Company, LLC
50.0 MWWithdrawn / abandoned Columbia, NYNYISO Oct 2019
Wading River Energy Center
Battery storage · Clean Energy Generation, LLC
50.0 MWWithdrawn / abandoned Suffolk, NYNYISO Nov 2020
Tierken Storage
Battery storage · Tierken Storage 1, LLC
50.0 MWWithdrawn / abandoned Rensselaer, NYNYISO Sep 2024
Chautauqua Windpower
Onshore wind · Chautauqua Windpower, LLC
50.0 MWWithdrawn / abandoned Chautauqua, NYNYISO May 2002
Lock 26 BESS
Battery storage · Oriden
50.0 MWWithdrawn / abandoned Wayne, NYNYISO Oct 2024
Kce NY 27
Battery storage · KCE NY 27, LLC
50.0 MWWithdrawn / abandoned Suffolk, NYNYISO Sep 2024
Long Island Storage Center I
Battery storage · Anbaric Development Partners, LLC
50.0 MWWithdrawn / abandoned Suffolk, NYNYISO Jul 2021
Appleseed Energy Storage
Battery storage · esVolta, LP
50.0 MWWithdrawn / abandoned Greene, NYNYISO Feb 2019
Icebox Energy Storage
Battery storage · GCI Icebox Energy Storage, LLC
50.0 MWWithdrawn / abandoned Onondaga, NYNYISO Aug 2024
Mount Hope Stand Alone Storage
Battery storage · Mount Hope Stand Alone Storage 1, LLC
50.0 MWWithdrawn / abandoned Orange, NYNYISO Nov 2022
Deerpark Energy Storage
Battery storage · Oriden LLC
50.0 MWWithdrawn / abandoned Orange, NYNYISO Sep 2021
Babylon Storage
Battery storage · Empire Reserve Energy, LLC
50.0 MWWithdrawn / abandoned Suffolk, NYNYISO Oct 2022
Holtsville West Storage, LLC
Battery storage · Holtsville West Storage LLC
50.0 MWWithdrawn / abandoned Suffolk, NYNYISO Dec 2021
Watson Storage System #2
Battery storage · Watson Storage LLC
50.0 MWWithdrawn / abandoned Queens, NYNYISO Feb 2023
Marshville BESS
Battery storage · Oriden
50.0 MWWithdrawn / abandoned Montgomery, NYNYISO Oct 2024
Chazy Lake BESS
Battery storage · Oriden
50.0 MWWithdrawn / abandoned Clinton, NYNYISO Oct 2024
Kce NY 31
Battery storage · KCE NY 31, LLC
50.0 MWWithdrawn / abandoned Suffolk, NYNYISO Oct 2022
Sidecar
Solar · ACE DevCo NC LLC
50.0 MWWithdrawn / abandoned Tioga, NYNYISO Sep 2024
Watson Storage System #1
Battery storage · Watson Storage LLC
50.0 MWWithdrawn / abandoned Queens, NYNYISO Feb 2023
Porter Energy Storage
Battery storage · BPUS Generation Development LLC
50.0 MWWithdrawn / abandoned Essex, NYNYISO Oct 2023
Glenwood Power Station Battery Energy Storage System (BESS)
Battery storage · National Grid Generation LLC
50.0 MWWithdrawn / abandoned Nassau, NYNYISO Sep 2024
Saltgrass Storage
Battery storage · Saltgrass Storage LLC
50.0 MWWithdrawn / abandoned Nassau, NYNYISO Sep 2024
Greene County
Solar · Hecate Energy, LLC
50.0 MWWithdrawn / abandoned Greene, NYNYISO Aug 2016
Mill Creek Wind Plant
Other · Mill Creek Wind Plant, LLC
50.0 MWWithdrawn / abandoned NYNYISO Sep 2000
Saugerties Energy Storage
Battery storage · Saugerties Energy Storage
50.0 MWWithdrawn / abandoned Ulster, NYNYISO Jan 2024
CBB Park
Battery storage · CBB PARK LLC
50.0 MWWithdrawn / abandoned Dutchess, NYNYISO Jan 2021
Mount Hope Storage
Battery storage · Mount Hope Stand Alone Storage 1, LLC
50.0 MWWithdrawn / abandoned Orange, NYNYISO Sep 2024
Hudson Valley Data Center
Other · Equity Suffern Developers, LLC
50.0 MWWithdrawn / abandoned Rockland, NYNYISO Apr 2024
Deerpark Energy Storage
Battery storage · Deerpark Energy Storage, LLC
50.0 MWWithdrawn / abandoned Orange, NYNYISO Oct 2024
Glenwood Power Station Battery Energy Storage System
Battery storage · National Grid Generation LLC
50.0 MWWithdrawn / abandoned Nassau, NYNYISO Nov 2019
West Babylon Power Station Battery Energy Storage System
Battery storage · National Grid Generation LLC
50.0 MWWithdrawn / abandoned Suffolk, NYNYISO Jan 2020
Winterberry Wind
Onshore wind · Winterberry Wind LLC
50.0 MWWithdrawn / abandoned Bradford, PANYISO Oct 2024
Steuben Wind
Onshore wind · EC&R Northeast, LLC
50.0 MWWithdrawn / abandoned Steuben, NYNYISO Oct 2003
Bethpage Storage
Battery storage · Calpine Mid Atlantic Development, LLC
50.0 MWWithdrawn / abandoned Nassau, NYNYISO Aug 2018
Gloversville Storage
Battery storage · Gloversville Storage, LLC
50.0 MWWithdrawn / abandoned Fulton, NYNYISO Sep 2022
Harvest Hills Solar II
Solar · ConnectGen Cayuga County LLC
50.0 MWWithdrawn / abandoned Cayuga, NYNYISO Aug 2021
Keesog Solar
Solar · Cypress Creek Renewables
50.0 MWWithdrawn / abandoned Franklin, NYNYISO Jan 2017
Fort Drum Gen Exp.
Other · NIMO/Black River Power
50.0 MWWithdrawn / abandoned NYNYISO Mar 2000
Line Creek Solar
Solar · sPower Development Company, LLC
50.0 MWWithdrawn / abandoned Schoharie, NYNYISO Oct 2019
Azalea Wind 2
Onshore wind · Azalea Wind LLC
50.0 MWWithdrawn / abandoned Schuyler, NYNYISO Sep 2024
Intrepid Storage 69
Battery storage · Hecate Grid Intrepid 1 LLC
50.0 MWWithdrawn / abandoned Nassau, NYNYISO Oct 2019
Scio Solar Facility
Solar + storage · Quantum DPI Group
50.0 MWWithdrawn / abandoned Allegany, NYNYISO Aug 2024
Wading River Power Station Battery Energy Storage System (BESS)
Battery storage · National Grid Generation LLC
50.0 MWWithdrawn / abandoned Suffolk, NYNYISO Sep 2024
Middletown Energy Storage
Battery storage · Oriden LLC
50.0 MWWithdrawn / abandoned Orange, NYNYISO Sep 2021
Page 20 of 31

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)