BATTERY STORAGE · NYISOTierken Storage
Tierken Storage is a 50.0 MW battery storage request withdrawn in the NYISO interconnection queue, in Rensselaer County, New York, connecting to NM-NG.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2024 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- C24-277
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NM-NG
- Developer
- Tierken Storage 1, LLC
- Connection point (POI)
- Reynolds Road - Greenbush 115 kV Line #9
- Location
- Rensselaer County, New York
- Technology
- Battery: 50.0 MW
- Total requested
- 50.0 MW
- Queue status
- Withdrawn
- Entered queue
- 24 September 2024
Location
Marker shows the centre of Rensselaer County; the queue data does not give exact sites.
Other requests in Rensselaer County
- Willard Storage (NYISO-C24-148)Battery storage · 300 MW · in study
- Willard StorageBattery storage · 300 MW · in study
- SolarSolar · 20.0 MW · in study
- Hilltop SolarSolar · 20.0 MW · in study
- CS Hawthorn SolarSolar · 20.0 MW · in study
- Empire GeneratingGas · 635 MW · built
- Empire GeneratingGas · 635 MW · built
- StephentownBattery storage · 20.0 MW · built
- StephentownBattery storage · 20.0 MW · built
- Knickerbocker Energy StorageBattery storage · 300 MW · withdrawn
- Topaz Storage ProjectBattery storage · 200 MW · withdrawn
- Honey Bee Battery Storage, LLCBattery storage · 199 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem