BATTERY STORAGE Β· NYISO

CBB Park

CBB Park is a 50.0 MW battery storage request withdrawn in the NYISO interconnection queue, in Dutchess County, New York, connecting to CHGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2021 (completed)
  2. Withdrawn / abandonedJul 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1127
Grid region
NYISO (New York)
Utility / transmission owner
CHGE
Developer
CBB PARK LLC
Connection point (POI)
Pleasant Valley 115 kV
Location
Dutchess County, New York
Technology
Battery: 50.0 MW
Total requested
50.0 MW
Queue status
Withdrawn
Entered queue
20 January 2021
Withdrawn
July 2021

Location

Marker shows the centre of Dutchess County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Dutchess County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem