GAS · NYISO

Cricket Valley Energy Center

Cricket Valley Energy Center is a 1,136 MW gas request withdrawn in the NYISO interconnection queue, in Dutchess County, New York, connecting to ConEd.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2008 (completed)
  2. Withdrawn / abandonedDec 2014 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
310
Grid region
NYISO (New York)
Utility / transmission owner
ConEd
Developer
Cricket Valley Energy Center, LLC
Connection point (POI)
Pleasant Valley - Long Mt. 345kV
Location
Dutchess County, New York
Technology
Gas: 1,136 MW
Total requested
1,136 MW
Queue status
Withdrawn
Entered queue
22 September 2008
Withdrawn
December 2014

Location

Marker shows the centre of Dutchess County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Dutchess County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem