United States › Grid › Interconnection queues › New York
GAS · ISO-NECricket Valley Project (QP444 in NYISO Queue)
Cricket Valley Project (QP444 in NYISO Queue) is a 1,020 MW gas request built and operating in the ISO-NE interconnection queue, in Dutchess County, New York.
Request details
- Queue ID
- 487
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- Pleasant Valley - Long Mtn 345 kV
- Location
- Dutchess County, New York
- Technology
- Gas: 1,020 MW
- Total requested
- 1,020 MW
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 18 December 2014
- Proposed online date
- April 2020
Location
Marker shows the centre of Dutchess County; the queue data does not give exact sites.
Other requests in Dutchess County
- East FishkillBattery storage · 205 MW · in study
- Highbush Energy StorageBattery storage · 200 MW · in study
- Overlook StorageBattery storage · 199 MW · in study
- Aria Storage 2Battery storage · 150 MW · in study
- Aria Storage 1Battery storage · 100 MW · in study
- Cricket Valley Energy Center IIGas · 1,132 MW · built
- Cricket Valley Energy Center IIGas · 1,132 MW · built
- Cricket Valley Energy CenterGas · 1,136 MW · withdrawn
- Dover NY BESSBattery storage · 1,000 MW · withdrawn
- Dover NY BESS (NYISO-C24-316)Battery storage · 1,000 MW · withdrawn
- Wingdale Energy CenterGas · 650 MW · withdrawn
- Agate Storage ProjectBattery storage · 200 MW · withdrawn