Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown8214.4 GW
Active in queue52.5 GW240 requests
Agreement signed14.4 GW82 requests
Withdrawn467102.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

82 requests · page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2017-061, Mayes County
Solar
102 MWAgreement signed Mayes, OKSPP May 20172025
Solar project GEN-2016-030, Johnston County
Solar
100 MWAgreement signed Johnston, OKSPP Mar 2016target 2026
Onshore wind project GEN-2016-139, Texas County
Onshore wind
100 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Battery storage project GEN-2018-024, Muskogee County
Battery storage
100 MWAgreement signed Muskogee, OKSPP May 2018target 2028
Battery storage project GEN-2019-002, Mayes County
Battery storage
100 MWAgreement signed Mayes, OKSPP Nov 2018target 2027
Battery storage project GEN-2018-026, Canadian County
Battery storage
100 MWAgreement signed Canadian, OKSPP May 2018target 2026
Battery storage project GEN-2018-027, Tulsa County
Battery storage
100 MWAgreement signed Tulsa, OKSPP May 2018target 2028
Battery storage project GEN-2021-041, Canadian County
Battery storage
100 MWAgreement signed Canadian, OKSPP Apr 2021target 2027
Battery storage project GEN-2021-001, Bryan County
Battery storage
100 MWAgreement signed Bryan, OKSPP Dec 2020target 2029
Battery storage project GEN-2018-029, Oklahoma County
Battery storage
100 MWAgreement signed Oklahoma, OKSPP May 2018target 2028
Battery storage project GEN-2020-SR2, Johnston County
Battery storage
100 MWAgreement signed Johnston, OKSPP Aug 2020target 2026
Onshore wind project GI-96, Lincoln County
Onshore wind
97.5 MWAgreement signed Lincoln, OKSoutheast Oct 2021target 2026
Gas project GEN-2023-GR1, Caddo County
Gas
97.5 MWAgreement signed Caddo, OKSPP Jan 20232025
Gas project GEN-2023-GR2, Oklahoma County
Gas
94.2 MWAgreement signed Oklahoma, OKSPP Feb 2023target 2026
Battery storage project GEN-2023-SR5, Dewey County
Battery storage
85.0 MWAgreement signed Dewey, OKSPP Dec 2022target 2026
Solar project GEN-2017-023, Choctaw County
Solar
85.0 MWAgreement signed Choctaw, OKSPP May 2017target 2026
Battery storage project GEN-2021-052, Muskogee County
Battery storage
75.0 MWAgreement signed Muskogee, OKSPP Apr 2021target 2031
Battery storage project GEN-2021-019, Noble County
Battery storage
74.9 MWAgreement signed Noble, OKSPP Apr 2021target 2028
Battery storage project GEN-2018-011, Kingfisher County
Battery storage
74.1 MWAgreement signed Kingfisher, OKSPP Apr 2018target 2027
Battery storage project GEN-2024-SR3, Lincoln County
Battery storage
72.5 MWAgreement signed Lincoln, OKSPP Feb 2024target 2026
Solar project GEN-2017-230, Lincoln County
Solar
72.5 MWAgreement signed Lincoln, OKSPP Nov 2017target 2027
Solar project GEN-2017-074, Mayes County
Solar
72.5 MWAgreement signed Mayes, OKSPP May 20172025
Solar project GEN-2017-073, Mayes County
Solar
72.5 MWAgreement signed Mayes, OKSPP May 20172025
Battery storage project GEN-2023-SR16, Woodward County
Battery storage
70.0 MWAgreement signed Woodward, OKSPP Apr 20232025
Onshore wind project GEN-2016-071, Kay County
Onshore wind
64.6 MWAgreement signed Kay, OKSPP Mar 2016target 2028
Solar project GEN-2017-072, Payne County
Solar
52.2 MWAgreement signed Payne, OKSPP May 20172025
Solar project GEN-2017-232, Bryan County
Solar
52.2 MWAgreement signed Bryan, OKSPP Nov 2017target 2026
Gas project GI-78, Mayes County
Gas
52.0 MWAgreement signed Mayes, OKSoutheast Jan 2019target 2020
Battery storage project GEN-2017-178, Garfield County
Battery storage
52.0 MWAgreement signed Garfield, OKSPP Nov 20172025
Gas project GI-77, Mayes County
Gas
50.0 MWAgreement signed Mayes, OKSoutheast Jan 2019target 2019
Solar project GEN-2017-173, Comanche County
Solar
50.0 MWAgreement signed Comanche, OKSPP Nov 2017target 2027
Solar project GEN-2017-172, Comanche County
Solar
50.0 MWAgreement signed Comanche, OKSPP Nov 2017target 2027
Page 2 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)