Battery storage project GEN-2020-SR2, Johnston County

Battery storage project GEN-2020-SR2, Johnston County is a 100 MW battery storage request with a signed interconnection agreement in the SPP interconnection queue, in Johnston County, Oklahoma, connecting to OGE.

Queue statusConsented
  1. PlanningQueued Aug 2020 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2020-SR2
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
Brown 138kV
Location
Johnston County, Oklahoma
Technology
Battery: 100 MW
Total requested
100 MW
Service type
NRIS and ERIS
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
4 August 2020
Proposed online date
March 2026

Location

Marker shows the centre of Johnston County; the queue data does not give exact sites.