Requests shown34960.6 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

349 requests · page 2 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GI-2016-4, Lincoln County
Onshore wind
300 MWAgreement signed Lincoln, COWest Feb 2016target 2018
Battery storage project 632, Owyhee County
Battery storage · NextEra Energy Resources Interconnection Holdings, LLC
300 MWAgreement signed Owyhee, IDWest Jan 2022target 2025
Battery storage project Q280, Maricopa County
Battery storage
300 MWAgreement signed Maricopa, AZWest Sep 2018target 2022
Solar + storage project 573, Power County
Solar + storage · NextEra Energy Resources Interconnection Holdings, LLC
300 MWAgreement signed Power, IDWest Nov 2019target 2027
Other project CLPT G16, Platte County
Other · NextEra Energy Resources Interconnection Holdings, LLC
300 MWAgreement signed Platte, WYWest Apr 2022target 2025
Solar + storage project Company MA, White Pine County
Solar + storage
300 MWAgreement signed White Pine, NVWest Sep 2021target 2028
Onshore wind project BHBE G13, Custer County
Onshore wind
300 MWAgreement signed Custer, NEWest Jul 2017target 2023
Solar + storage project IA-PNM-2021-10, Bernalillo County
Solar + storage · NextEra Energy
300 MWAgreement signed Bernalillo, NMWest Jul 2021target 2025
Coal project BHBE G4, Campbell County
Coal · Basin Electric
300 MWAgreement signed Campbell, SDWest Jan 2005target 2011
Solar + storage project C1-39, Washington County
Solar + storage · REBU BN, LLC
300 MWAgreement signed Washington, UTWest May 2021target 2027
Solar + storage project Company MH, Churchill County
Solar + storage
300 MWAgreement signed Churchill, NVWest Sep 2021target 2024
Wind + storage project CS24-15, Lincoln County
Wind + storage
300 MWAgreement signed Lincoln, WAWest Apr 2024target 2029
AW300S
Solar
300 MWAgreement signed Sierra, NMWest Mar 2023target 2029
Solar project Q06, San Bernardino County
Solar
300 MWAgreement signed San Bernardino, CAWest Mar 2008target 2023
Battery storage project Q375, Maricopa County
Battery storage
300 MWAgreement signed Maricopa, AZWest Mar 2021target 2023
Solar + storage project Company 165, Clark County
Solar + storage
300 MWAgreement signed Clark, NVWest Sep 2018target 2026
Solar project BHBE G19, Campbell County
Solar
300 MWAgreement signed Campbell, SDWest May 2022target 2024
Solar + storage project C2-82, Bannock County
Solar + storage · BRP Garnet 1, LLC
300 MWAgreement signed Bannock, IDWest May 2022target 2027
Solar + storage project GI-DISIS-2022-02, Weld County
Solar + storage
299 MWAgreement signed Weld, COWest May 2022target 2030
Solar + storage project GI-DISIS-2022-07, Weld County
Solar + storage
299 MWAgreement signed Weld, COWest May 2022target 2029
Onshore wind project BHBE G16, Campbell County
Onshore wind
290 MWAgreement signed Campbell, WYWest Dec 2021target 2024
Solar + storage project Company 195, Clark County
Solar + storage
275 MWAgreement signed Clark, NVWest Mar 2021target 2023
Gas project GI-2006-1d, Weld County
Gas
269 MWAgreement signed Weld, COWest Jan 2006target 2007
Solar project CLPT G18, Converse County
Solar · DUTC bn, LLC
255 MWAgreement signed Converse, WYWest Jun 2022target 2024
LH252W
Onshore wind
252 MWAgreement signed Grant, NMWest Mar 2023target 2027
Onshore wind project 2019-G2
Onshore wind
252 MWAgreement signed West Nov 2018target 2022
Onshore wind project 2019-G1
Onshore wind
252 MWAgreement signed West Nov 2018target 2021
Coal project BHBE G1, Campbell County
Coal · Basin Electric
250 MWAgreement signed Campbell, SDWest Feb 2001target 2011
Solar + storage project GI-2018-24, Pueblo County
Solar + storage
250 MWAgreement signed Pueblo, COWest Aug 20182022
Solar project Company NR, Lassen County
Solar
250 MWAgreement signed Lassen, CAWest Sep 2022target 2030
Battery storage project Company 237, Clark County
Battery storage
250 MWAgreement signed Clark, NVWest Jan 2023target 2026
Onshore wind project G0294, Columbia County
Onshore wind
250 MWAgreement signed Columbia, WAWest Oct 2007target 2011
Solar + storage project Company KN, Humboldt County
Solar + storage
250 MWAgreement signed Humboldt, NVWest Aug 2020target 2024
Onshore wind project GI-TC-2024-15, Laramie County
Onshore wind
250 MWAgreement signed Laramie, WYWest May 2024target 2029
Sf250SB
Solar + storage
250 MWAgreement signed Hudspeth, TXWest Sep 2023target 2028
Onshore wind project GI-2007-13, Lincoln County
Onshore wind
250 MWAgreement signed Lincoln, COWest Nov 2007target 2009
Solar project BHBE G20, Dawes County
Solar
250 MWAgreement signed Dawes, SDWest Jul 2022target 2025
Onshore wind project GI-2007-12, El Paso County
Onshore wind
250 MWAgreement signed El Paso, COWest Nov 2007target 2010
Onshore wind project G0295, Columbia County
Onshore wind
250 MWAgreement signed Columbia, WAWest Oct 2007target 2011
Solar + storage project 2RSC-2020-05, Pueblo County
Solar + storage
250 MWAgreement signed Pueblo, COWest Sep 2020target 2022
Solar + storage project 21-098, Jefferson County
Solar + storage
250 MWAgreement signed Jefferson, ORWest Apr 2021target 2034
Solar + storage project Q295, Pinal County
Solar + storage
250 MWAgreement signed Pinal, AZWest Mar 2019target 2022
EC500W Project
Onshore wind
247 MWAgreement signed Chaves, NMWest Jul 2017target 2020
Onshore wind project GI-2004-2, Baca County
Onshore wind
238 MWAgreement signed Baca, COWest Feb 2004
Solar + storage project GI-DISIS-2022-04, Kit Carson County
Solar + storage
237 MWAgreement signed Kit Carson, COWest May 2022target 2027
Gas project IA-PNM-2017-14, San Juan County
Gas
236 MWAgreement signed San Juan, NMWest Oct 2017target 2022
Geothermal project Company LM, Lyon County
Geothermal
230 MWAgreement signed Lyon, NVWest Mar 2021target 2029
Gas project Company 230, Clark County
Gas
222 MWAgreement signed Clark, NVWest Sep 2022target 2024
Gas project Company 231, Clark County
Gas
222 MWAgreement signed Clark, NVWest Sep 2022target 2024
Onshore wind project CS23-06, Whitman County
Onshore wind
221 MWAgreement signed Whitman, WAWest Apr 2023target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)