United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in CAISO (California) — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,186619.9 GW
Active in queue188.6 GW429 requests
Agreement signed96.2 GW235 requests
Withdrawn2,186619.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,186 requests · page 2 of 44
ProjectCapacityStatusLocationRegionQueuedOnline
Una Lake Solar
Solar + storage
1,243 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2019target 2022
Magic Valley Wind 1
Wind + storage
1,239 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Colima Hybrid Solar
Solar + storage
1,212 MWWithdrawn / abandoned Kern, CACAISO Apr 2021target 2026
Redwood Coast Offshore Wind 2
Offshore wind
1,206 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Redwood Coast Offshore Wind 1
Offshore wind
1,206 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Whispering Sands Solar
Solar + storage
1,202 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Morro Bay Modernization Project
Gas
1,200 MWWithdrawn / abandoned San Luis Obispo, CACAISO Dec 2000target 2008
Ses Solar Seven
Solar
1,200 MWWithdrawn / abandoned San Bernardino, CACAISO Aug 2006target 2011
Sunvale Solar Farm
Solar + storage
1,200 MWWithdrawn / abandoned Clark, NVCAISO Apr 2018target 2022
Herculean
Solar + storage
1,198 MWWithdrawn / abandoned CACAISO Apr 2023target 2031
Meson
Solar + storage
1,191 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
MidBishop Energy Storage
Battery storage
1,191 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Las Brisas Offshore Wind
Offshore wind
1,188 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2019target 2026
Titan Power
Battery storage
1,160 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Tesla Power Plant
Gas
1,156 MWWithdrawn / abandoned San Joaquin, CACAISO Aug 2000target 2014
Alta 12
Onshore wind
1,150 MWWithdrawn / abandoned Los Angeles, CACAISO May 2008target 2013
Alta 13
Solar
1,150 MWWithdrawn / abandoned San Bernardino, CACAISO May 2008target 2013
Wingtip Solar 2
Solar + storage
1,123 MWWithdrawn / abandoned Merced, CACAISO Apr 2021target 2027
Nightcap
Gas
1,122 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2023target 2028
Elixir
Gas
1,101 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Hideout
Gas
1,101 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
City Of Vernon Renewable Project 2
Other
1,100 MWWithdrawn / abandoned Kern, CACAISO Jul 2009target 2012
Taurus Wind
Wind + storage
1,088 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Suncrest Imperial Segs
Solar
1,080 MWWithdrawn / abandoned Imperial, CACAISO Mar 2011target 2015
Central Valley I Segs
Solar
1,080 MWWithdrawn / abandoned Kern, CACAISO Mar 2011target 2015
Blackbird
Solar + storage
1,057 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Egret
Solar + storage
1,057 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Heron
Solar + storage
1,056 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Rio Hondo Power
Gas
1,047 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2013target 2019
Heartland Solar-2
Solar
1,045 MWWithdrawn / abandoned Fresno, CACAISO May 2016target 2020
Heartland Solar
Solar
1,045 MWWithdrawn / abandoned Fresno, CACAISO May 2016target 2020
FiveGB
Solar + storage
1,041 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Red Star Grizzly Offshore Wind
Offshore wind
1,040 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2021target 2028
Algodones Storage
Battery storage
1,039 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Harquahala Sunrise 3
Solar + storage
1,038 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Mercator
Solar + storage
1,037 MWWithdrawn / abandoned Fresno, CACAISO Apr 2018target 2021
Solo
Solar + storage
1,037 MWWithdrawn / abandoned Riverside, CACAISO Apr 2019target 2022
Diablo Sands Energy Storage
Battery storage
1,036 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
La Paz 2
Solar + storage
1,034 MWWithdrawn / abandoned Maricopa, AZCAISO Apr 2021target 2028
Rumorosa Wind
Onshore wind
1,029 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Water Canyon Wind
Onshore wind
1,029 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2021target 2028
Sunnynook Solar Center
Solar + storage
1,029 MWWithdrawn / abandoned Riverside, CACAISO Apr 2019target 2026
Skylar Verano Solar
Solar + storage
1,027 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Glyder
Solar + storage
1,026 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Adobe Flats
Solar + storage
1,024 MWWithdrawn / abandoned La Paz, AZCAISO Apr 2021target 2025
Pitchfork Energy
Solar + storage
1,024 MWWithdrawn / abandoned Maricopa, AZCAISO Apr 2018target 2024
Descendant Ranch 2
Solar + storage
1,024 MWWithdrawn / abandoned Colusa, CACAISO Apr 2018target 2023
Western Coast Wind 1
Offshore wind
1,021 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2020target 2027
Amargosa SEZ
Solar + storage
1,019 MWWithdrawn / abandoned Nye, NVCAISO Apr 2023target 2030
Frontera
Solar + storage
1,018 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Page 2 of 44

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)