OFFSHORE WIND · CAISO

Western Coast Wind 1

Western Coast Wind 1 is a 1,021 MW offshore wind request withdrawn in the CAISO interconnection queue, in San Luis Obispo County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2020 (completed)
  2. Withdrawn / abandonedMar 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1748
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Diablo Canyon - Morro Bay 230 kV and Diablo Canyon - Mesa 230 kV Lines
Location
San Luis Obispo County, California
Technology
Offshore Wind: 1,021 MW
Total requested
1,021 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
15 April 2020
Proposed online date
April 2027
Withdrawn
March 2021

Location

Marker shows the centre of San Luis Obispo County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Luis Obispo County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem