Requests shown96364.7 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

963 requests · page 17 of 20
ProjectCapacityStatusLocationRegionQueuedOnline
Hydro project 542, Twin Falls County
Hydro · Koyle Hydro Inc
1.4 MWOperating Twin Falls, IDWest Oct 2018target 2019
Other project KOYL, Gooding County
Other
1.3 MWOperating Gooding, IDWest
Hydro project 382, Canyon County
Hydro
1.3 MWOperating Canyon, IDWest Jul 20112012
Onshore wind project BHCT G24, Huerfano County
Onshore wind · Black Hills Electric Generation LLC
1.3 MWOperating Huerfano, COWest Sep 2018target 2020
Hydro project 410, Gooding County
Hydro
1.3 MWOperating Gooding, IDWest Jul 2013target 2016
Hydro project 409, Jerome County
Hydro
1.3 MWOperating Jerome, IDWest Jul 2013target 2016
Other project hist_q41, Jerome County
Other
1.2 MWOperating Jerome, IDWest
Battery storage project 42, Whitman County
Battery storage
1.2 MWOperating Whitman, WAWest Nov 2014target 2015
Hydro project 494, Lincoln County
Hydro
1.2 MWOperating Lincoln, IDWest May 2015target 2016
Onshore wind project 299, Cassia County
Onshore wind
1.2 MWOperating Cassia, IDWest Sep 20092010
Hydro project 585, Twin Falls County
Hydro · White Marco Power Company
1.2 MWOperating Twin Falls, IDWest Nov 2019target 2020
Hydro project 606, Lincoln County
Hydro · Arkoosh Hydro Inc
1.1 MWOperating Lincoln, IDWest Jun 2021target 2021
Hydro project 299, Klamath County
Hydro · C-Drop Hydro, LLC
1.1 MWOperating Klamath, ORWest Oct 2009target 2012
Whitefish In-Line Hydroelectric Project
Hydro
1.0 MWOperating Flathead, MTWest Jan 2012target 2012
Onshore wind project GI-0510, Hanson County
Onshore wind · Oak Lane
1.0 MWOperating Hanson, SDWest Aug 2005target 2007
Onshore wind project 162, Meagher County
Onshore wind
1.0 MWOperating Meagher, MTWest Apr 20132013
Arlington Microgrid
Solar + storage
1.0 MWOperating Snohomish, WAWest Jun 2018target 2019
Farm Power Misty Meadow
Other · Farm Power Misty Meadow, LLC
1.0 MWOperating Tillamook, ORWest Feb 2011target 2011
Hydro project 150, Salt Lake County
Hydro · Cottonwood Hydro
1.0 MWOperating Salt Lake, UTWest Jul 2007target 2009
Outback
Solar · Outback Solar, LLC
1.0 MWOperating Lake, ORWest Aug 2010target 2010
Onshore wind project 195, Elmore County
Onshore wind
1.0 MWOperating Elmore, IDWest Jun 2007target 2008
Battery storage project 852, Tooele County
Battery storage · Tooele Army Depot
1.0 MWOperating Tooele, UTWest Mar 2017target 2018
Onshore wind project 196, Elmore County
Onshore wind
1.0 MWOperating Elmore, IDWest Jun 2007target 2008
UEC Solar PV Array
Solar
1.0 MWOperating Umatilla, ORWest Apr 2015target 2015
Battery storage project 919, Garfield County
Battery storage · PacifiCorp Energy Supply Management
1.0 MWOperating Garfield, UTWest Jul 2017target 2020
Other project GI-0516, Deuel County
Other
1.0 MWOperating Deuel, SDWest Oct 2005target 2005
Farm Power Tillamook
Other · Farm Power Tillamook LLC
1.0 MWOperating Tillamook, ORWest Mar 2011target 2011
Decatur Island Solar
Solar
1.0 MWOperating San Juan, WAWest Apr 2018target 2018
Hardeson Battery Storage Expansion
Battery storage
1.0 MWOperating Snohomish, WAWest Oct 2014target 2015
Hydro project 599, Lincoln County
Hydro · Arkoosh Hydro Inc
1.0 MWOperating Lincoln, IDWest Jan 2021target 2021
Other project G0470, Yamhill County
Other
1.0 MWOperating Yamhill, ORWest Mar 2012target 2012
Ross MHQ Solar Project
Solar
1.0 MWOperating Clark, WAWest Jul 2017target 2017
King Estate Solar Generator Project
Solar
1.0 MWOperating Lane, ORWest May 2008target 2008
Hardeson Battery Storage
Battery storage
1.0 MWOperating Snohomish, WAWest May 2013target 2014
Solar project 630, Davis County
Solar · Smith's Food & Drug Stores, Inc.
1.0 MWOperating Davis, UTWest Oct 2014target 2015
Sisters Irrigation Hydro Project
Hydro
1.0 MWOperating Deschutes, ORWest Oct 2011target 2013
Onshore wind project 93, Tooele County
Onshore wind · Tooele Army Depot
1.0 MWOperating Tooele, UTWest Sep 2006target 2008
Rock Creek Hydro Project
Hydro · Rock Creek Hydro LLC
1.0 MWOperating Custer, IDWest Dec 2018target 2019
McKenzie Reservoir Hydroelectric Facility
Hydro
1.0 MWOperating Deschutes, ORWest Aug 2017target 2018
Hydro project hist_q34, Lincoln County
Hydro
0.9 MWOperating Lincoln, IDWest
Hydro project 545, Gooding County
Hydro · Carroll Family Enterprises Inc.
0.9 MWOperating Gooding, IDWest Nov 2018target 2019
Hydro project 574, Twin Falls County
Hydro · Snake River Pottery Power Company, Inc
0.9 MWOperating Twin Falls, IDWest Oct 2019target 2019
Other project KSWS, Twin Falls County
Other
0.9 MWOperating Twin Falls, IDWest
Other project FALK, Gooding County
Other
0.9 MWOperating Gooding, IDWest
Hydro project 637, Gooding County
Hydro · Faulkner Brothers Hydro
0.9 MWOperating Gooding, IDWest Feb 2022target 2022
Other project GOB2, Lincoln County
Other
0.9 MWOperating Lincoln, IDWest
Other project 99, Polk County
Other · Meduri Farms, Inc.
0.8 MWOperating Polk, ORWest Oct 2006target 2007
Hydro project 584, Twin Falls County
Hydro · Russell LeMoyne
0.8 MWOperating Twin Falls, IDWest Jun 2020target 2020
Hydro project 548, Lemhi County
Hydro · Coleman Hydro
0.8 MWOperating Lemhi, IDWest Feb 20192023
Solar project 581, Klamath County
Solar · Klamath Falls Solar 1, LLC
0.8 MWOperating Klamath, ORWest Jun 2014target 2016
Page 17 of 20

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)