United States › Grid › Interconnection queues › Idaho
HYDRO · WESTHydro project 548, Lemhi County
Hydro project 548, Lemhi County is a 0.8 MW hydro request built and operating in the West interconnection queue, in Lemhi County, Idaho, connecting to Idaho Power Company.
Request details
- Queue ID
- 548
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Idaho Power Company
- Developer
- Coleman Hydro
- Connection point (POI)
- LMHI 34.5kV Feeder
- Location
- Lemhi County, Idaho
- Technology
- Hydro: 0.8 MW
- Total requested
- 0.8 MW
- Service type
- Other
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 22 February 2019
- Agreement signed
- 21 July 2021
- Proposed online date
- October 2023
- Came online
- October 2023
Location
Marker shows the centre of Lemhi County; the queue data does not give exact sites.
Other requests in Lemhi County
- Hydro project 600, Lemhi CountyHydro · 0.5 MW · built
- Hydro project hist_q58, Lemhi CountyHydro · 0.5 MW · built
- Hydro project 406, Lemhi CountyHydro · 0.5 MW · built
- Other project hist_q65, Lemhi CountyOther · 0.1 MW · built
- Hydro project 362, Lemhi CountyHydro · 1.0 MW · withdrawn
- Hydro project 407, Lemhi CountyHydro · 0.8 MW · withdrawn
- Hydro project 67, Lemhi CountyHydro · 0.6 MW · withdrawn
- Hydro project 366, Lemhi CountyHydro · 0.5 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem