King Estate Solar Generator Project

King Estate Solar Generator Project is a 1.0 MW solar request built and operating in the West interconnection queue, in Lane County, Oregon, connecting to Lane Electric Cooperative, Inc..

Queue statusOperating
  1. PlanningQueued May 2008 (completed)
  2. ConsentedDec 2011 (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2008 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G0332
Grid region
West (non-ISO utilities)
Utility / transmission owner
Lane Electric Cooperative, Inc.
Connection point (POI)
Integrating in Lane Electric Coop's system (Fox Hollow Substation)
Location
Lane County, Oregon
Technology
Solar: 1.0 MW
Total requested
1.0 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
19 May 2008
Agreement signed
20 December 2011
Proposed online date
December 2008

Location

Marker shows the centre of Lane County; the queue data does not give exact sites.