Sisters Irrigation Hydro Project

Sisters Irrigation Hydro Project is a 1.0 MW hydro request built and operating in the West interconnection queue, in Deschutes County, Oregon, connecting to Three Sisters Irrigation District.

Queue statusOperating
  1. PlanningQueued Oct 2011 (completed)
  2. ConsentedApr 2013 (completed)
  3. Construction (completed)
  4. OperatingTarget Sep 2013 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G0466
Grid region
West (non-ISO utilities)
Utility / transmission owner
Three Sisters Irrigation District
Connection point (POI)
68000 Hwy 20 W, Bend, OR 97701
Location
Deschutes County, Oregon
Technology
Hydro: 1.0 MW
Total requested
1.0 MW
Service type
Energy only (ERIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
4 October 2011
Agreement signed
24 April 2013
Proposed online date
September 2013

Location

Marker shows the centre of Deschutes County; the queue data does not give exact sites.

Power plants in Oregon · Transmission lines in Oregon

Other requests in Deschutes County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem