🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Utah

ONSHORE WIND · WEST

Onshore wind project 93, Tooele County

Onshore wind project 93, Tooele County is a 1.0 MW onshore wind request built and operating in the West interconnection queue, in Tooele County, Utah, connecting to PacifiCorp.

Queue statusOperating
  1. PlanningQueued Sep 2006 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Mar 2008 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
93
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Tooele Army Depot
Connection point (POI)
Customer's electric system from TEAD substation
Location
Tooele County, Utah
Technology
Wind: 1.0 MW
Total requested
1.0 MW
Service type
Network resource (NRIS)
Study phase
No IA necessary
Queue status
Operational
Entered queue
19 September 2006
Proposed online date
March 2008

Location

Marker shows the centre of Tooele County; the queue data does not give exact sites.

Power plants in Utah · Transmission lines in Utah

Other requests in Tooele County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem