Onshore wind project GI-0510, Hanson County is a 1.0 MW onshore wind request built and operating in the West interconnection queue, in Hanson County, South Dakota, connecting to WAPA/BEPC/HCPD Integrated System.
Request details
- Queue ID
- GI-0510
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- WAPA/BEPC/HCPD Integrated System
- Developer
- Oak Lane
- Connection point (POI)
- Mt. Vernon
- Location
- Hanson County, South Dakota
- Technology
- Wind: 1.0 MW
- Total requested
- 1.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- IAE/IS
- Queue status
- Operational
- Entered queue
- 9 August 2005
- Proposed online date
- January 2007
Location
Marker shows the centre of Hanson County; the queue data does not give exact sites.
Power plants in South Dakota · Transmission lines in South Dakota
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem