United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2024 requests) — page 16

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,313251.4 GW
Active in queue285.2 GW1,283 requests
Agreement signed30.3 GW117 requests
Withdrawn1,313251.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,313 requests · page 16 of 27
ProjectCapacityStatusLocationRegionQueuedOnline
Battery Storage + Solar
Solar + storage
101 MWWithdrawn / abandoned Franklin, MAISO-NE Apr 2024target 2027
Kobernat Solar
Solar · BT Kobernat Solar, LLC
101 MWWithdrawn / abandoned Starr, TXERCOT Feb 2024target 2026
Battery storage project 24-241, Columbia County
Battery storage
100 MWWithdrawn / abandoned Columbia, ORWest Apr 2024target 2027
Wallkill Energy Storage
Battery storage · ACE DevCo NC,LLC
100 MWWithdrawn / abandoned Ulster, NYNYISO Sep 2024
Kce NY 41
Battery storage · KCE NY 41, LLC
100 MWWithdrawn / abandoned Suffolk, NYNYISO Sep 2024
Battery storage project J3334, Laporte County
Battery storage
100 MWWithdrawn / abandoned Laporte, INMISO Apr 2024target 2028
WEB Addison Solar
Solar · SWEB Development USA LLC
100 MWWithdrawn / abandoned Steuben, NYNYISO Oct 2024
Battery storage project J3506, Pike County
Battery storage
100 MWWithdrawn / abandoned Pike, ILMISO Apr 2024target 2028
Battery storage project J3453, Holmes County
Battery storage
100 MWWithdrawn / abandoned Holmes, MSMISO Apr 2024target 2028
Battery storage project 625, Indian River County
Battery storage · FPL
100 MWWithdrawn / abandoned Indian River, FLSoutheast Jan 2024target 2032
Cruiser BESS
Battery storage · Viridity Energy Solutions
100 MWWithdrawn / abandoned Suffolk, NYNYISO Sep 2024
Arch 1
Battery storage · Terra-Gen Development Company, LLC
100 MWWithdrawn / abandoned Orange, NYNYISO Aug 2024
Battery storage project 616, Putnam County
Battery storage · FPL
100 MWWithdrawn / abandoned Putnam, FLSoutheast Jan 2024target 2028
Solar project J3365, Tangipahoa Parish County
Solar
100 MWWithdrawn / abandoned Tangipahoa Parish, LAMISO Mar 2024target 2028
Solar project J3463, Jefferson County
Solar
100 MWWithdrawn / abandoned Jefferson, MSMISO Apr 2024target 2026
Solar project C4-069, Power County
Solar · PacifiCorp
100 MWWithdrawn / abandoned Power, IDWest May 2024target 2029
Battery storage project J3351, Putnam County
Battery storage
100 MWWithdrawn / abandoned Putnam, ILMISO Apr 2024target 2028
Battery storage project J3692, Cheboygan County
Battery storage
100 MWWithdrawn / abandoned Cheboygan, MIMISO Apr 2024target 2028
Solar + storage project 639, Jackson County
Solar + storage
100 MWWithdrawn / abandoned Jackson, ALSoutheast Aug 2024
Sketch Book Storage
Battery storage · Sketch Book Storage 1, LLC
100 MWWithdrawn / abandoned Columbia, NYNYISO Aug 2024
Solar project J3788, Grant County
Solar
100 MWWithdrawn / abandoned Grant, ARMISO Apr 2024target 2028
Battery storage project J3312, Washington County
Battery storage
100 MWWithdrawn / abandoned Washington, MNMISO Apr 2024target 2028
Battery storage project J3698, Roscommon County
Battery storage
100 MWWithdrawn / abandoned Roscommon, MIMISO Apr 2024target 2028
North Catskill DG LLC
Battery storage · BayWa r.e Projects LLC.
100 MWWithdrawn / abandoned Greene, NYNYISO Aug 2024
Moran 2
Solar · ACE DevCo NC LLC
100 MWWithdrawn / abandoned Fulton, NYNYISO Sep 2024
Solar project J3531, White County
Solar
100 MWWithdrawn / abandoned White, ARMISO Apr 2024target 2027
Deer River Wind
Onshore wind · Deer River Wind, LLC
100 MWWithdrawn / abandoned Lewis, NYNYISO Sep 2024
Battery storage project C4-077, Salt Lake County
Battery storage
100 MWWithdrawn / abandoned Salt Lake, UTWest May 2024target 2027
Solar project GEN-2024-001, Curry County
Solar
100 MWWithdrawn / abandoned Curry, NMSPP Feb 2024target 2029
Battery storage project J3358, Dewitt County
Battery storage
100 MWWithdrawn / abandoned Dewitt, ILMISO Apr 2024target 2028
Orchard BESS
Battery storage · Empire Reserve Energy, LLC
100 MWWithdrawn / abandoned Ulster, NYNYISO Aug 2024
Battery storage project 151, Pierce County
Battery storage
100 MWWithdrawn / abandoned Pierce, WAWest Apr 2024target 2027
Dix Hills Storage, LLC
Battery storage · Dix Hills Storage, LLC
100 MWWithdrawn / abandoned Suffolk, NYNYISO Aug 2024
Solar project J3641, Dickinson County
Solar
100 MWWithdrawn / abandoned Dickinson, MIMISO Apr 2024target 2028
Solar + storage project C4-047, Millard County
Solar + storage
100 MWWithdrawn / abandoned Millard, UTWest May 2024target 2027
Zenobe Rotterdam LLC (NYISO-C24-191)
Battery storage
100 MWWithdrawn / abandoned Schenectady, NYISO-NE Dec 2024target 2028
Solar project J3406, Calcasieu Parish County
Solar
100 MWWithdrawn / abandoned Calcasieu Parish, LAMISO Apr 2024target 2028
Onshore wind project J3779, Henderson County
Onshore wind
100 MWWithdrawn / abandoned Henderson, KYMISO Apr 2024target 2026
Zenobe Rotterdam LLC
Battery storage · Zenobe Rotterdam LLC
100 MWWithdrawn / abandoned Schenectady, NYNYISO Sep 2024
Battery storage project 144, Skagit County
Battery storage
100 MWWithdrawn / abandoned Skagit, WAWest Apr 2024target 2027
Battery storage project J3665, Redwood County
Battery storage
100 MWWithdrawn / abandoned Redwood, MNMISO Apr 2024target 2028
Battery storage project C4-079, Multnomah County
Battery storage
100 MWWithdrawn / abandoned Multnomah, ORWest May 2024target 2027
Crossbuck Energy Storage, LLC
Battery storage · BayWa r.e Projects LLC.
100 MWWithdrawn / abandoned Greene, NYNYISO Aug 2024
Dunkirk Energy Storage
Battery storage · BGTF US Development Holdings LLC
100 MWWithdrawn / abandoned Chautauqua, NYNYISO Sep 2024
Arch 1
Battery storage · Terra-Gen Development, LLC
100 MWWithdrawn / abandoned Orange, NYNYISO Aug 2024
Bull Run Solar
Solar · Bull Run Solar LLC
100 MWWithdrawn / abandoned Clinton, NYNYISO Aug 2024
Solar project J3683, Scott County
Solar
100 MWWithdrawn / abandoned Scott, ILMISO Apr 2024target 2028
Battery storage project J3670, Lasalle County
Battery storage
100 MWWithdrawn / abandoned Lasalle, ILMISO Apr 2024target 2028
Medina Solar
Solar · ACE DevCo NC LLC
100 MWWithdrawn / abandoned Orleans, NYNYISO Sep 2024
Battery storage project CS24-04, Spokane County
Battery storage
100 MWWithdrawn / abandoned Spokane, WAWest Apr 2024target 2028
Page 16 of 27

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)