United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

BATTERY STORAGE Β· MISO

Battery storage project J3692, Cheboygan County

Battery storage project J3692, Cheboygan County is a 100 MW battery storage request withdrawn in the MISO interconnection queue, in Cheboygan County, Michigan, connecting to METC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandonedSep 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3692
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
PORT CALCITE - RIGGSVILLE 138.0kV
Location
Cheboygan County, Michigan
Technology
Battery: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Withdrawn
Entered queue
18 April 2024
Proposed online date
May 2028
Withdrawn
September 2025

Location

Marker shows the centre of Cheboygan County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Cheboygan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem