United States βΊ Grid βΊ Interconnection queues βΊ Michigan
SOLAR Β· MISOSolar project J832, Cheboygan County
Solar project J832, Cheboygan County is a 100 MW solar request withdrawn in the MISO interconnection queue, in Cheboygan County, Michigan, connecting to METC.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2017 (completed)
- Withdrawn / abandonedJun 2021 (project stopped here)
- ConsentedJun 2020 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J832
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- METC
- Connection point (POI)
- Port Calcite - Riggsville 138kV Line
- Location
- Cheboygan County, Michigan
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 16 June 2017
- Agreement signed
- 12 June 2020
- Proposed online date
- December 2022
- Withdrawn
- June 2021
Location
Marker shows the centre of Cheboygan County; the queue data does not give exact sites.
Other requests in Cheboygan County
- Solar project J1929, Cheboygan CountySolar Β· 110 MW Β· in study
- Solar project J3777, Cheboygan CountySolar Β· 91.8 MW Β· in study
- Other project G212 CONS 105, Cheboygan CountyOther Β· 200 MW Β· withdrawn
- Battery storage project J3692, Cheboygan CountyBattery storage Β· 100 MW Β· withdrawn
- Solar project J3668, Cheboygan CountySolar Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem