United States βΊ Grid βΊ Interconnection queues βΊ New York
ONSHORE WIND Β· NYISODeer River Wind
Deer River Wind is a 100 MW onshore wind request withdrawn in the NYISO interconnection queue, in Lewis County, New York, connecting to NM-NG.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2024 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- C24-297
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NM-NG
- Developer
- Deer River Wind, LLC
- Connection point (POI)
- Black River-Lighthouse Hill Line 5 115kV
- Location
- Lewis County, New York
- Technology
- Wind: 100 MW
- Total requested
- 100 MW
- Queue status
- Withdrawn
- Entered queue
- 27 September 2024
Location
Marker shows the centre of Lewis County; the queue data does not give exact sites.
Other requests in Lewis County
- Sugar Maple SolarSolar Β· 125 MW Β· in study
- Flat Rock Wind PowerOnshore wind Β· 321 MW Β· built
- Flat Rock Wind PowerOnshore wind Β· 321 MW Β· built
- Number 3 Wind EnergyOnshore wind Β· 104 MW Β· built
- Number 3 Wind EnergyOnshore wind Β· 104 MW Β· built
- Copenhagen WindOnshore wind Β· 79.9 MW Β· built
- Copenhagen WindOnshore wind Β· 79.9 MW Β· built
- Roaring Brook WindOnshore wind Β· 79.7 MW Β· built
- Roaring Brook WindOnshore wind Β· 79.7 MW Β· built
- Chinook Energy Storage CenterBattery storage Β· 500 MW Β· withdrawn
- Antelope Energy Storage CenterBattery storage Β· 500 MW Β· withdrawn
- Chinook Energy Storage CenterBattery storage Β· 500 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem