Withdrawn queue requests in the USA — page 143

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 143 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Riverline Energy Center
Battery storage · Riverline Energy Center, LLC
200 MWWithdrawn / abandoned St. Lawrence, NYNYISO Jun 2020
Onshore wind project G605, Montgomery County
Onshore wind
200 MWWithdrawn / abandoned Montgomery, INMISO Feb 2006target 2008
Solar project J3096, Henderson County
Solar
200 MWWithdrawn / abandoned Henderson, KYMISO Sep 2022target 2025
Cunningham Solar 1
Solar · Invenergy
200 MWWithdrawn / abandoned Lamar, TXERCOT Apr 2018target 2023
Onshore wind project H003, Mcdonough County
Onshore wind
200 MWWithdrawn / abandoned Mcdonough, ILMISO Sep 2010target 2009
Solar project J2774, Ionia County
Solar
200 MWWithdrawn / abandoned Ionia, MIMISO Aug 2024target 2026
Gas project G352, Dakota County
Gas
200 MWWithdrawn / abandoned Dakota, MNMISO Jul 2003target 2011
Solar project J2935, Saginaw County
Solar
200 MWWithdrawn / abandoned Saginaw, MIMISO Sep 2022target 2025
Van Oker
Battery storage
200 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Solar project J3345, Moultrie County
Solar
200 MWWithdrawn / abandoned Moultrie, ILMISO Apr 2024target 2028
Onshore wind project G0337, Klickitat County
Onshore wind
200 MWWithdrawn / abandoned Klickitat, WAWest Jul 2008target 2011
AREW Old Forge
Hydro
200 MWWithdrawn / abandoned Luzerne, PAPJM Jul 2018target 2027
Solar project AH1-146, Ogle County
Solar · Mound Solar, LLC
200 MWWithdrawn / abandoned Ogle, ILPJM Feb 2025target 2025
Solar project J1527, Ottawa County
Solar
200 MWWithdrawn / abandoned Ottawa, MIMISO Jun 2020target 2026
Onshore wind project GEN-2015-071, Beckham County
Onshore wind
200 MWWithdrawn / abandoned Beckham, OKSPP Oct 20152021
Solar project AH1-240, Boone County
Solar
200 MWWithdrawn / abandoned Boone, KYPJM Sep 2021target 2024
Onshore wind project G0354, Meagher County
Onshore wind
200 MWWithdrawn / abandoned Meagher, MTWest Mar 2009target 2014
Solar project 459, Big Horn County
Solar
200 MWWithdrawn / abandoned Big Horn, MTWest May 2024target 2029
Onshore wind project GI-2008-9, Sedgwick County
Onshore wind
200 MWWithdrawn / abandoned Sedgwick, COWest Jun 2008target 2010
Battery storage project J2449, Faulkner County
Battery storage
200 MWWithdrawn / abandoned Faulkner, ARMISO Sep 2022target 2026
Onshore wind project J630, Deuel County
Onshore wind
200 MWWithdrawn / abandoned Deuel, SDMISO May 2016target 2019
Solar + storage project IC-833, Decatur County
Solar + storage
200 MWWithdrawn / abandoned Decatur, GASoutheast Oct 2019
Solar project J1909, Bay County
Solar
200 MWWithdrawn / abandoned Bay, MIMISO Aug 2021target 2023
Battery storage project J3557, Morgan County
Battery storage
200 MWWithdrawn / abandoned Morgan, INMISO Apr 2024target 2028
Solar project GEN-2022-181, Tillman County
Solar
200 MWWithdrawn / abandoned Tillman, OKSPP Feb 2023target 2026
Solar project AG2-165, Marshall County
Solar · Wahoo Solar LLC
200 MWWithdrawn / abandoned Marshall, INPJM Feb 2025target 2024
Battery storage project IC-830, Fulton County
Battery storage
200 MWWithdrawn / abandoned Fulton, GASoutheast Oct 2019
Onshore wind project GEN-2006-032, Ellis County
Onshore wind
200 MWWithdrawn / abandoned Ellis, KSSPP Aug 2006target 2007
Battery storage project J3662, Monroe County
Battery storage
200 MWWithdrawn / abandoned Monroe, ILMISO Apr 2024target 2028
Onshore wind project GEN-2007-033, Hutchinson County
Onshore wind
200 MWWithdrawn / abandoned Hutchinson, TXSPP Aug 2007target 2009
BPP NY Somerset BESS I
Battery storage · Bear Peak Power
200 MWWithdrawn / abandoned Niagara, NYNYISO Sep 2023
Battery storage project J3502, Van Buren County
Battery storage
200 MWWithdrawn / abandoned Van Buren, MIMISO Apr 2024target 2028
Onshore wind project G890, Fillmore County
Onshore wind
200 MWWithdrawn / abandoned Fillmore, MNMISO Oct 2007target 2008
Solar project IC-681, Harrison County
Solar
200 MWWithdrawn / abandoned Harrison, MSSoutheast Mar 2018
Solar + storage project GEN-2023-098, Perkins County
Solar + storage
200 MWWithdrawn / abandoned Perkins, SDSPP Oct 2023target 2027
Solar project J2664, Montgomery County
Solar
200 MWWithdrawn / abandoned Montgomery, INMISO Sep 2022target 2026
Great Republic Wind Generation Project
Onshore wind · Great Republic Power Partners LLC
200 MWWithdrawn / abandoned ERCOT Dec 2005target 2050
Iberdrola Renewables Inc
Onshore wind · Avangrid Power, LLC
200 MWWithdrawn / abandoned Klickitat, ORWest Nov 2002target 2004
Battery storage project 107, Pierce County
Battery storage
200 MWWithdrawn / abandoned Pierce, WAWest Apr 2021target 2023
Battery storage project J3581, Avoyelles Parish County
Battery storage
200 MWWithdrawn / abandoned Avoyelles Parish, LAMISO Apr 2024target 2028
Onshore wind project G614, Emmet County
Onshore wind
200 MWWithdrawn / abandoned Emmet, IAMISO Mar 2006target 2009
Solar project J2319, Huron County
Solar
200 MWWithdrawn / abandoned Huron, MIMISO Aug 2021target 2023
Solar project J1640, Hinds County
Solar
200 MWWithdrawn / abandoned Hinds, MSMISO Jun 2020target 2023
Canela Energy Storage
Battery storage
200 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Battery storage project 136, Pima County
Battery storage
200 MWWithdrawn / abandoned Pima, AZWest Sep 2022target 2027
Milliken
Gas
200 MWWithdrawn / abandoned Riverside, CACAISO Apr 2007target 2010
Battery storage project AH1-738, Prince George's County
Battery storage · Lighthouse Keys, LLC
200 MWWithdrawn / abandoned Prince George's, MDPJM target 2029
Solar + storage project J2356, Craighead County
Solar + storage
200 MWWithdrawn / abandoned Craighead, ARMISO Sep 2022target 2026
Scandia Wind E
Onshore wind · Scandia Southwest
200 MWWithdrawn / abandoned ERCOT Jun 2009target 2017
Onshore wind project G670, Faribault County
Onshore wind
200 MWWithdrawn / abandoned Faribault, MNMISO Oct 2010target 2011
Page 143 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)