OCTARY USA · INTERCONNECTION QUEUES

Completed queue projects in PJM (Mid-Atlantic, Midwest) — page 13

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,19297.6 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,192 requests · page 13 of 24
ProjectCapacityStatusLocationRegionQueuedOnline
Marcal Paper
Gas
20.0 MWOperating Bergen, NJPJM Jan 20072007
Morris Cogen
Gas
20.0 MWOperating Grundy, ILPJM Aug 20142016
Keystone Generating Station
Coal
20.0 MWOperating Indiana, PAPJM Dec 20072010
Coal project U1-032, City Of Hopewell County
Coal
20.0 MWOperating City Of Hopewell, VAPJM Feb 20082009
Braidwood Nuclear Generating Station, Unit 1
Nuclear
20.0 MWOperating Will, ILPJM Dec 20092014
Byron Nuclear Generating Station, Unit 2
Nuclear
20.0 MWOperating Ogle, ILPJM Dec 20092014
Elizabeth City Solar
Solar
20.0 MWOperating Camden, NCPJM Feb 20162021
Rockport Unit 1
Coal
20.0 MWOperating Spencer, INPJM Jan 20072011
Braidwood Nuclear Generating Station, Unit 2
Nuclear
20.0 MWOperating Will, ILPJM Dec 20092014
Hardin Energy Center
Solar
20.0 MWOperating Hardin, OHPJM Aug 20092020
Pleasant Hill Solar
Solar
20.0 MWOperating City Of Suffolk, VAPJM Dec 20192023
North Anna Unit 2
Nuclear
20.0 MWOperating Louisa, VAPJM Jul 20072010
Conemaugh Generating Station
Coal
20.0 MWOperating Indiana, PAPJM May 20102012
Cottontail Solar 8
Solar
20.0 MWOperating York, PAPJM Sep 20182024
Rockford I Energy Center
Gas
20.0 MWOperating Winnebago, ILPJM Oct 20162021
Darbytown GT2
Gas
20.0 MWOperating Henrico, VAPJM Jul 20072008
Conemaugh Generating Station
Coal
20.0 MWOperating Indiana, PAPJM May 20102012
Oak Hall Project D
Solar
20.0 MWOperating VAPJM Feb 20102016
Milan Energy
Gas
19.9 MWOperating Lackawanna, PAPJM Oct 20132017
Aulander Holloman Solar Park
Solar
19.9 MWOperating Hertford, NCPJM Jun 20182020
Woodbine Road Solar
Solar
19.9 MWOperating Westmoreland, VAPJM Mar 20182021
Beaver Dam Generating Station
Gas
19.9 MWOperating Bradford, PAPJM Oct 20132016
Nickel Solar
Solar
19.9 MWOperating Warren, OHPJM Oct 20192024
Lightfoot 34.5 kV II
Solar
19.9 MWOperating James City, VAPJM Sep 20182022
Camellia Solar
Solar
19.9 MWOperating Gloucester, VAPJM Jan 20202025
Wyalusing 34.5kV
Gas
19.9 MWOperating Bradford, PAPJM Apr 20152019
Pilesgrove SP
Solar
19.9 MWOperating Salem, NJPJM Jul 20092011
Glory Barn Road Generating Facility Alpaca
Gas
19.9 MWOperating Bradford, PAPJM Dec 20132017
Meherrin Solar
Solar
19.8 MWOperating Greensville, VAPJM Oct 20152022
Jade Meadow
Solar
19.8 MWOperating Allegany, MDPJM Apr 20192024
Solar project AB2-029, Fauquier County
Solar
19.8 MWOperating Fauquier, VAPJM Feb 20162017
Gloucester Solar
Solar
19.8 MWOperating Gloucester, VAPJM Dec 20172019
Meherrin Solar
Solar
19.8 MWOperating Greensville, VAPJM Oct 20152022
VESI – Andover Energy Storage
Battery storage
19.8 MWOperating Sussex, NJPJM Jul 20182023
Mount Olive Solar Farm
Solar
19.8 MWOperating Morris, NJPJM Mar 20202023
Solar project AB2-045, Buckingham County
Solar
19.8 MWOperating Buckingham, VAPJM Feb 20162017
Pondtown Solar 1
Solar
19.8 MWOperating Queen Anne's, MDPJM Oct 20152022
Pondtown Solar 1
Solar
19.8 MWOperating Queen Anne's, MDPJM Oct 20152022
Gas project X4-046
Gas
19.5 MWOperating DCPJM Jan 20122019
GSA Federal Research Center (FDA)
Gas
19.5 MWOperating Montgomery, MDPJM Dec 20052007
Calvert Cliffs Units 1 and 2 (f/k/a PJM Queue M04)
Nuclear
19.2 MWOperating Calvert, MDPJM Jun 20162023
Lorain
Other
19.2 MWOperating Lorain, OHPJM Nov 20102012
Chesterfield Unit #5
Coal
19.0 MWOperating Chesterfield, VAPJM Jan 20072011
Gravel Neck Gas Turbine #5
Gas
19.0 MWOperating Surry, VAPJM Jul 20072010
Montpelier
Gas
19.0 MWOperating Wells, INPJM Mar 20072008
Gravel Neck Gas Turbine #3
Gas
19.0 MWOperating Surry, VAPJM Jul 20072010
Ladysmith Combustion Turbines Unit 1
Gas
19.0 MWOperating Caroline, VAPJM Mar 20172019
Gravel Neck Gas Turbine #6
Gas
19.0 MWOperating Surry, VAPJM Jul 20072010
Ladysmith Combustion Turbines Unit 2
Gas
19.0 MWOperating Caroline, VAPJM Mar 20172019
Gravel Neck Gas Turbine #4
Gas
19.0 MWOperating Surry, VAPJM Jul 20072010
Page 13 of 24

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)