🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Virginia

GAS · PJM

Gravel Neck Gas Turbine #5

Gravel Neck Gas Turbine #5 is a 19.0 MW gas request built and operating in the PJM interconnection queue, in Surry County, Virginia, connecting to Dominion.

Queue statusOperating
  1. PlanningQueued Jul 2007 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingMay 2010 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
S84
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Surry 230kV
Location
Surry County, Virginia
Technology
Gas: 19.0 MW
Total requested
19.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
31 July 2007
Proposed online date
May 2010
Came online
May 2010

Location

Marker shows the centre of Surry County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Surry County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem