United States › Grid › Interconnection queues › Virginia

SOLAR · PJM

Lightfoot 34.5 kV II

Lightfoot 34.5 kV II is a 19.9 MW solar request built and operating in the PJM interconnection queue, in James City County, Virginia, connecting to Dominion.

Queue statusOperating
  1. PlanningQueued Sep 2018 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingMay 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AE1-175
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
Light Foot 34.5 kV
Location
James City County, Virginia
Technology
Solar: 19.9 MW
Total requested
19.9 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Operational
Entered queue
25 September 2018
Proposed online date
November 2021
Came online
May 2022

Location

Marker shows the centre of James City County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in James City County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem