United States › Grid › Interconnection queues › Virginia
SOLAR · PJMLightfoot 34.5 kV II
Lightfoot 34.5 kV II is a 19.9 MW solar request built and operating in the PJM interconnection queue, in James City County, Virginia, connecting to Dominion.
Request details
- Queue ID
- AE1-175
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Light Foot 34.5 kV
- Location
- James City County, Virginia
- Technology
- Solar: 19.9 MW
- Total requested
- 19.9 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Operational
- Entered queue
- 25 September 2018
- Proposed online date
- November 2021
- Came online
- May 2022
Location
Marker shows the centre of James City County; the queue data does not give exact sites.
Other requests in James City County
- Battery storage project AH1-716, James City CountyBattery storage · 650 MW · in study
- Norge SolarSolar · 20.0 MW · built
- Battery storage project AH1-726, James City CountyBattery storage · 600 MW · withdrawn
- Battery storage project AG2-322, James City CountyBattery storage · 150 MW · withdrawn
- Solar project AG1-032, James City CountySolar · 20.0 MW · withdrawn
- Battery storage project AE1-174, James City CountyBattery storage · 5.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem