United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in the USA (2018 requests) โ page 12
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Oakdale Battery Storage Battery storage ยท Oakdale Battery Storage LLC |
120 MW | Withdrawn / abandoned |
| Solar project LGE-GIS-2018-003, Hart County Solar |
120 MW | Withdrawn / abandoned |
| Solar project AE1-159, Caroline County Solar |
120 MW | Withdrawn / abandoned |
| Solar + storage project Company IK, Humboldt County Solar + storage |
120 MW | Withdrawn / abandoned |
| Solar project AD2-120, Mercer County Solar |
120 MW | Withdrawn / abandoned |
| Solar project IC-691, Forrest County Solar |
120 MW | Withdrawn / abandoned |
| Solar + storage project AE1-128, Bedford County Solar + storage |
120 MW | Withdrawn / abandoned |
| Solar project IC-682, Lamar County Solar |
120 MW | Withdrawn / abandoned |
| Reiher Solar Solar ยท EnergieKontor US Texas SP 7 LLC |
120 MW | Withdrawn / abandoned |
| Solar project J985, Scott County Solar |
120 MW | Withdrawn / abandoned |
| Solar project LGE-GIS-2018-004, Union County Solar |
120 MW | Withdrawn / abandoned |
| Solar project LGE-GIS-2018-009, Larue County Solar |
120 MW | Withdrawn / abandoned |
| Pflugerville 2 Solar Solar ยท RRE Power LLC 1 |
120 MW | Withdrawn / abandoned |
| Solar project IC-718, Charlton County Solar |
120 MW | Withdrawn / abandoned |
| Solar project LGE-GIS-2018-007, Fleming County Solar |
120 MW | Withdrawn / abandoned |
| Solar project IC-764, Terrell County Solar |
120 MW | Withdrawn / abandoned |
| Solar project AE1-232, Chesterfield County Solar |
120 MW | Withdrawn / abandoned |
| Solar project 1000, Weber County Solar |
120 MW | Withdrawn / abandoned |
| Solar project AE1-158, Caroline County Solar |
120 MW | Withdrawn / abandoned |
| Solar project J1163, Quitman County Solar |
120 MW | Withdrawn / abandoned |
| Solar + storage project 18-10101, Weld County Solar + storage |
120 MW | Withdrawn / abandoned |
| Solar project Company 158, Clark County Solar |
117 MW | Withdrawn / abandoned |
| Friendswood II Gas ยท Friendswood Energy 2 |
117 MW | Withdrawn / abandoned |
| Adamstown Storage Other ยท Adams Creek Solar Project, LLC |
117 MW | Withdrawn / abandoned |
| Solar project G0604, Yakima County Solar |
115 MW | Withdrawn / abandoned |
| Solar + storage project Q26, Maricopa County Solar + storage |
115 MW | Withdrawn / abandoned |
| Solar project IC-709, Jefferson County Solar |
115 MW | Withdrawn / abandoned |
| Scioto Farms Solar Project Solar |
110 MW | Withdrawn / abandoned |
| Solar + storage project GI-2018-29, Adams County Solar + storage |
110 MW | Withdrawn / abandoned |
| Hood 1 Solar |
110 MW | Withdrawn / abandoned |
| Solar + storage project 64, Adams County Solar + storage |
110 MW | Withdrawn / abandoned |
| DRY Creek Solar Solar |
110 MW | Withdrawn / abandoned |
| Solar + storage project G0600, Grant County Solar + storage |
108 MW | Withdrawn / abandoned |
| Solar project IC-766, Screven County Solar |
107 MW | Withdrawn / abandoned |
| Solar project 63, Thurston County Solar |
105 MW | Withdrawn / abandoned |
| Gas project AD2-165, Middlesex County Gas |
105 MW | Withdrawn / abandoned |
| Solar project GI-69, Kingfisher County Solar |
105 MW | Withdrawn / abandoned |
| Wind Onshore wind |
104 MW | Withdrawn / abandoned |
| Wind Onshore wind |
104 MW | Withdrawn / abandoned |
| Wind Onshore wind |
104 MW | Withdrawn / abandoned |
| Wind Onshore wind |
104 MW | Withdrawn / abandoned |
| Wind Onshore wind |
104 MW | Withdrawn / abandoned |
| Dernopi Solar Solar |
103 MW | Withdrawn / abandoned |
| Onshore wind project G0580, Morrow County Onshore wind |
103 MW | Withdrawn / abandoned |
| Energy Storage Battery storage |
103 MW | Withdrawn / abandoned |
| Stephen Solar |
103 MW | Withdrawn / abandoned |
| Solar project GEN-2018-056, Knox County Solar |
103 MW | Withdrawn / abandoned |
| Prickly Pear Solar ยท EnergieKontor US TEXAS SP 13 LLC |
103 MW | Withdrawn / abandoned |
| Poleline Solar Energy Center Solar + storage |
102 MW | Withdrawn / abandoned |
| Solar project AE1-064, Bedford County Solar |
102 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)306 ยท 50.5 GW
- PJM (Mid-Atlantic, Midwest)311 ยท 46.6 GW
- MISO (Midcontinent)165 ยท 28.2 GW
- Southeast (non-ISO utilities)248 ยท 28.2 GW
- CAISO (California)67 ยท 21.7 GW
- SPP (Southwest Power Pool)92 ยท 16.8 GW
- ERCOT (Texas)77 ยท 15.0 GW
- NYISO (New York)74 ยท 11.2 GW
- ISO-NE (New England)84 ยท 8,151 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)