United States › Grid › Interconnection queues › Indiana

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Indiana — page 12

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown579114.4 GW
Active in queue59.6 GW300 requests
Agreement signed11.2 GW69 requests
Withdrawn579114.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

579 requests · page 12 of 12
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project AH1-152, St. Joseph County
Battery storage · Dumont Solar, LLC
30.0 MWWithdrawn / abandoned St. Joseph, INPJM Aug 2021target 2025
Onshore wind project J1150, Miami County
Onshore wind
30.0 MWWithdrawn / abandoned Miami, INMISO Mar 2018target 2020
Battery storage project J1806, Henry County
Battery storage
30.0 MWWithdrawn / abandoned Henry, INMISO Jun 2020target 2022
Battery storage project AG1-376, Blackford County
Battery storage
30.0 MWWithdrawn / abandoned Blackford, INPJM Sep 2020target 2024
Battery storage project AH1-154, St. Joseph County
Battery storage · Dumont Solar, LLC
30.0 MWWithdrawn / abandoned St. Joseph, INPJM Aug 2021target 2025
Solar + storage project J2829, Scott County
Solar + storage
30.0 MWWithdrawn / abandoned Scott, INMISO Sep 2022target 2025
Battery storage project AE2-171, Madison County
Battery storage
30.0 MWWithdrawn / abandoned Madison, INPJM Mar 2019target 2022
Other project J224, Clay County
Other
29.5 MWWithdrawn / abandoned Clay, INMISO Aug 2011target 2014
Other project J065, Scott County
Other
29.0 MWWithdrawn / abandoned Scott, INMISO Aug 2009target 2011
Other project J012, Crawford County
Other
28.0 MWWithdrawn / abandoned Crawford, INMISO Jan 2009target 2007
Solar project J1318, Rush County
Solar
25.0 MWWithdrawn / abandoned Rush, INMISO Apr 2019target 2022
Battery storage project J1976, Porter County
Battery storage
25.0 MWWithdrawn / abandoned Porter, INMISO Mar 2022target 2025
Solar project J2894, Hendricks County
Solar
22.8 MWWithdrawn / abandoned Hendricks, INMISO Sep 2022target 2025
Battery storage project AA2-106, Jay County
Battery storage
20.0 MWWithdrawn / abandoned Jay, INPJM Apr 2015target 2018
Battery storage project AF1-080, Madison County
Battery storage
20.0 MWWithdrawn / abandoned Madison, INPJM Aug 2019target 2021
Battery storage project AC1-088, Madison County
Battery storage
20.0 MWWithdrawn / abandoned Madison, INPJM Oct 2016target 2017
Onshore wind project G887, Benton County
Onshore wind
20.0 MWWithdrawn / abandoned Benton, INMISO Oct 2007target 2012
Battery storage project AH1-742, Delaware County
Battery storage · Royerton Solar, LLC
20.0 MWWithdrawn / abandoned Delaware, INPJM target 2029
Royerton Solar and Storage
Battery storage · Royerton Solar, LLC
20.0 MWWithdrawn / abandoned Delaware, INPJM Mar 2020target 2023
Solar project J492, Montgomery County
Solar
20.0 MWWithdrawn / abandoned Montgomery, INMISO Nov 2015target 2017
Solar project J491, Bartholomew County
Solar
20.0 MWWithdrawn / abandoned Bartholomew, INMISO Nov 2015target 2017
Solar + storage project J2564, Montgomery County
Solar + storage
18.9 MWWithdrawn / abandoned Montgomery, INMISO Sep 2022target 2025
Onshore wind project G969, Benton County
Onshore wind
18.0 MWWithdrawn / abandoned Benton, INMISO Feb 2008target 2010
Battery storage project J1981, Gibson County
Battery storage
15.0 MWWithdrawn / abandoned Gibson, INMISO Aug 2021target 2025
Solar + storage project J2778, Miami County
Solar + storage
15.0 MWWithdrawn / abandoned Miami, INMISO Sep 2022target 2025
Battery storage project Y2-112, Wells County
Battery storage
12.0 MWWithdrawn / abandoned Wells, INPJM Nov 2012target 2013
Solar + storage project J2776, Fulton County
Solar + storage
10.0 MWWithdrawn / abandoned Fulton, INMISO Sep 2022target 2025
Other project J152, White County
Other
5.9 MWWithdrawn / abandoned White, INMISO Jun 2010target 2010
Other project AA1-063, Randolph County
Other
3.6 MWWithdrawn / abandoned Randolph, INPJM Sep 2014target 2016
Page 12 of 12

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)